'''Location:''' Sinnar village, Nasik district, Maharashtra<br>
 
'''Location:''' Sinnar village, Nasik district, Maharashtra<br>
 
'''Coordinates:'''  
 
'''Coordinates:'''  
* Phase I & 2, Units 1-5: 19.8666594, 74.0817493 (Exact); Unit 6: 19.9817, 73,8896<br>
+
* Phase I & 2, Units 1-5: 19.8666594, 74.0817493 (Exact);<br>
 +
* Unit 6: 19.9817, 73,8896<br>
 
'''Status:'''
 
'''Status:'''
 
* Phase I: Unit 1 - Operating February 2014;<br>  
 
* Phase I: Unit 1 - Operating February 2014;<br>  

Revision as of 22:53, 23 May 2014

{{#Badges:CoalSwarm|navbar-Indiacoal}}Nasik Thermal Power Project is a 2700 megawatt (MW) coal-fired power station being developed in two 1350 MW phases by Indiabulls Power Ltd.

Location

The undated satellite photo below shows construction activity at the site, which is located about 6 km east of Sinnar in Nasik district, Maharashtra.

Background

Nasik Thermal Power Project is a 2700 megawatt coal-fired power station being developed in two phases by Indiabulls Power Ltd. The power station is located in Sinnar, Nasik district, in Maharashtra, India. The company states that "coal linkage has been granted and letters of assurance from South Eastern Coalfields Ltd. (SECL), Western Coalfields Ltd. (WCL) and Mahanadi Coalfields Ltd. (MCL) have been issued."[1] The company also states that the project has achieved financial closure and that "construction is in full swing."[2] According to the September 2013 report of the Central Electricity Authority, construction had slipped significantly, with estimated completion of Phase I expected expected during 2014 and 2015 (see "Project Details" below for unit-by-unit commissioning estimates). As for Phase II, the report no longer lists the project as under construction.[3]

Project Details

Sponsor: Indiabulls Power
Location: Sinnar village, Nasik district, Maharashtra
Coordinates:

  • Phase I & 2, Units 1-5: 19.8666594, 74.0817493 (Exact);
  • Unit 6: 19.9817, 73,8896

Status:

  • Phase I: Unit 1 - Operating February 2014;
  • Phase I: Units 2-5 - Construction;
  • Phase II: Units 1-5 - Construction;
  • Phase II, Unit 6: Pre-permit development

Nameplate capacity: Phase I: 1350 MW (5 x 270 MW); Phase II: 1350 MW (5 x 270 MW); Unit 6: 660 MW
Type:
Projected in service:

  • Phase I - Unit 2: February 2014[3]
  • Phase I - Unit 3: November 2014[3]
  • Phase I - Unit 4: January 2015[3]
  • Phase I - Unit 5: March 2015[3]
  • Phase II - listed in September 2012 status report but not in September 2013 status report[3]

Coal Type:
Coal Source:
Estimated annual CO2:
Source of financing:
Permits and applications:

Resources

References

  1. Indiabulls Power, "Nasik Thermal Power Project", Indiabulls Power website, accessed November 2011.
  2. "Robust results for Indiabulls Power in FY 2011-12," Indiabulls press release, April 28, 2012
  3. Jump up to: 3.0 3.1 3.2 3.3 3.4 3.5 Monthly Report on Broad Status of Thermal Power Projects in the Country, Central Electricity Authority, February 2014

Related SourceWatch articles


External resources

External articles