Difference between revisions of "Nasik RattanIndia Thermal Power Project"
Line 10: | Line 10: | ||
In 2011 the company stated that "coal linkage has been granted and letters of assurance from South Eastern Coalfields Ltd. (SECL), Western Coalfields Ltd. (WCL) and Mahanadi Coalfields Ltd. (MCL) have been issued."<ref>Indiabulls Power, [http://www.indiabulls.com/power/nasik.htm "Nasik Thermal Power Project"], Indiabulls Power website, accessed November 2011.</ref> The company also stated that the project had achieved financial closure and that "construction is in full swing."<ref name=pr>[http://www.indiabulls.com/ibgroup/media.htm "Robust results for Indiabulls Power in FY 2011-12,"] Indiabulls press release, April 28, 2012</ref> | In 2011 the company stated that "coal linkage has been granted and letters of assurance from South Eastern Coalfields Ltd. (SECL), Western Coalfields Ltd. (WCL) and Mahanadi Coalfields Ltd. (MCL) have been issued."<ref>Indiabulls Power, [http://www.indiabulls.com/power/nasik.htm "Nasik Thermal Power Project"], Indiabulls Power website, accessed November 2011.</ref> The company also stated that the project had achieved financial closure and that "construction is in full swing."<ref name=pr>[http://www.indiabulls.com/ibgroup/media.htm "Robust results for Indiabulls Power in FY 2011-12,"] Indiabulls press release, April 28, 2012</ref> | ||
− | According to the September 2013 report of the Central Electricity Authority, construction had slipped significantly, with estimated completion of Phase I expected expected during 2014 and 2015 | + | According to the September 2013 report of the Central Electricity Authority, construction had slipped significantly, with estimated completion of Phase I expected expected during 2014 and 2015. As for Phase II, the report no longer lists the project as under construction.<ref name=broad>[http://www.cea.nic.in/reports/proj_mon/broad_status.pdf Monthly Report on Broad Status of Thermal Power Projects in the Country,] Central Electricity Authority, February 2014</ref><ref name=broad>[http://www.cea.nic.in/reports/proj_mon/broad_status.pdf Monthly Report on Broad Status of Thermal Power Projects in the Country,] Central Electricity Authority, June 2014</ref> |
+ | |||
+ | According to the February 2015 report of the Central Electricity Authority, Unit 1 was commissioned in February 2014, Unit 2 in March 2015, and Units 3-5 planned for late 2015 to early 2016. Phase II is no longer listed and appears to be delayed or abandoned.<ref>[http://www.cea.nic.in/reports/proj_mon/broad_status.pdf Broad Status Report], India Central Electrical Authority, February 2015</ref> | ||
==Project Details== | ==Project Details== | ||
Line 17: | Line 19: | ||
'''Coordinates:''' 19.8666594, 74.0817493 (exact)<br> | '''Coordinates:''' 19.8666594, 74.0817493 (exact)<br> | ||
'''Status:''' | '''Status:''' | ||
− | * Phase I, Unit 1-2: Operating (2014) | + | * Phase I, Unit 1-2: Operating (2014-5) |
* Phase I, Units 3-5: Construction | * Phase I, Units 3-5: Construction | ||
* Phase II, Units 1-5: Permitted | * Phase II, Units 1-5: Permitted | ||
Line 25: | Line 27: | ||
'''Type:''' <br> | '''Type:''' <br> | ||
'''Projected in service:''' | '''Projected in service:''' | ||
− | + | *Phase I, Unit 3: 2015 | |
− | *Phase I, Unit 3: | + | *Phase I, Unit 4: 2015 |
− | *Phase I, Unit 4: | + | *Phase I, Unit 5: 2016 |
− | *Phase I, Unit 5: | ||
− | |||
'''Coal Type:''' <br> | '''Coal Type:''' <br> | ||
'''Coal Source:''' <br> | '''Coal Source:''' <br> |
Revision as of 18:13, 16 April 2015
{{#Badges:CoalSwarm|navbar-Indiacoal}}Nasik Thermal Power Project is a proposed 2700 megawatt (MW) coal-fired power station in Maharashtra, India.
Contents
Location
The undated satellite photo below shows construction activity at the site, which is located about 6 km east of Sinnar in Nasik district.
Background
The power station is being developed in two phases by Indiabulls Power (later known as Nasik Power) in Sinnar, Nasik district. Phase I would be 1350 MW (5 x 270 MW) and Phase II: 1350 MW (5 x 270 MW).
In 2011 the company stated that "coal linkage has been granted and letters of assurance from South Eastern Coalfields Ltd. (SECL), Western Coalfields Ltd. (WCL) and Mahanadi Coalfields Ltd. (MCL) have been issued."[1] The company also stated that the project had achieved financial closure and that "construction is in full swing."[2]
According to the September 2013 report of the Central Electricity Authority, construction had slipped significantly, with estimated completion of Phase I expected expected during 2014 and 2015. As for Phase II, the report no longer lists the project as under construction.[3][3]
According to the February 2015 report of the Central Electricity Authority, Unit 1 was commissioned in February 2014, Unit 2 in March 2015, and Units 3-5 planned for late 2015 to early 2016. Phase II is no longer listed and appears to be delayed or abandoned.[4]
Project Details
Sponsor: Nasik Power (formerly Indiabulls Power)
Location: Sinnar village, Nasik district, Maharashtra
Coordinates: 19.8666594, 74.0817493 (exact)
Status:
- Phase I, Unit 1-2: Operating (2014-5)
- Phase I, Units 3-5: Construction
- Phase II, Units 1-5: Permitted
Nameplate capacity:
- Phase I: 1350 MW (5 x 270 MW)
- Phase II: 1350 MW (5 x 270 MW)
Type:
Projected in service:
- Phase I, Unit 3: 2015
- Phase I, Unit 4: 2015
- Phase I, Unit 5: 2016
Coal Type:
Coal Source:
Estimated annual CO2:
Source of financing:
Permits and applications:
- Phase I, Units: 1-5: Environmental Clearance, India MoEF, July 28, 2010
- Phase II, Units 1-5: Environmental Clearance, India MoEF, August 5, 2011
Resources
References
- ↑ Indiabulls Power, "Nasik Thermal Power Project", Indiabulls Power website, accessed November 2011.
- ↑ "Robust results for Indiabulls Power in FY 2011-12," Indiabulls press release, April 28, 2012
- ↑ Jump up to: 3.0 3.1 Monthly Report on Broad Status of Thermal Power Projects in the Country, Central Electricity Authority, February 2014 Cite error: Invalid
<ref>
tag; name "broad" defined multiple times with different content - ↑ Broad Status Report, India Central Electrical Authority, February 2015