− | {{#badges:CoalSwarm}} '''Pailin power station''' was a 200-megawatt (MW) proposed coal-fired power station in Krong Pailin, Cambodia. | + | {{#badges:CoalSwarm|Navbar-Cambodiacoal}}'''Pailin power station''' was a 200-megawatt (MW) proposed coal-fired power station in Krong Pailin, Cambodia. |
==Location== | ==Location== | ||
Line 8: | Line 8: | ||
In 2008 information-technology (IT) holding company Dragon One, announced plans to borrow about Bt20 billion from the Japan Bank for International Cooperation (JBIC) and other foreign banks to finance construction of a 200 MW power plant in Cambodia. The power was to be used in Cambodia and eastern Thailand. Construction was slated to commence in 2009 for completion in 2012.<ref>[http://www.nationmultimedia.com/2008/01/23/business/business_30063097.php "IT firm to construct power plant,"] The Nation, Jan 23, 2008.</ref> | In 2008 information-technology (IT) holding company Dragon One, announced plans to borrow about Bt20 billion from the Japan Bank for International Cooperation (JBIC) and other foreign banks to finance construction of a 200 MW power plant in Cambodia. The power was to be used in Cambodia and eastern Thailand. Construction was slated to commence in 2009 for completion in 2012.<ref>[http://www.nationmultimedia.com/2008/01/23/business/business_30063097.php "IT firm to construct power plant,"] The Nation, Jan 23, 2008.</ref> | ||
− | + | However, as of 2014 the project appears to have been cancelled. | |
==Project Details== | ==Project Details== |
Latest revision as of 03:22, 12 November 2014
{{#badges:CoalSwarm|Navbar-Cambodiacoal}}Pailin power station was a 200-megawatt (MW) proposed coal-fired power station in Krong Pailin, Cambodia.
Location
The map below shows Pailin Town, the approximate location where the plant would be built.
Loading map...
Background on Plant
In 2008 information-technology (IT) holding company Dragon One, announced plans to borrow about Bt20 billion from the Japan Bank for International Cooperation (JBIC) and other foreign banks to finance construction of a 200 MW power plant in Cambodia. The power was to be used in Cambodia and eastern Thailand. Construction was slated to commence in 2009 for completion in 2012.[1]
However, as of 2014 the project appears to have been cancelled.
Project Details
- Sponsor: Dragon Power
- Parent company:
- Developer:
- Location: Krong Pailin, Cambodia
- Coordinates: 12.850556, 102.609444 (approximate)
- Status: Cancelled
- Capacity: 200 MW
- Type: Subcritical
- Coal Type:
- Coal Source:
- Source of financing:
- Permits and applications:
Articles and resources
References
- ↑ "IT firm to construct power plant," The Nation, Jan 23, 2008.