Difference between revisions of "Uppada power station"
(fixed map) |
(clarifying) |
||
Line 1: | Line 1: | ||
− | {{#badges: CoalSwarm|Navbar-Indiacoal}} '''Uppada power station''' is a | + | {{#badges: CoalSwarm|Navbar-Indiacoal}} '''Uppada power station''' is an existing 208-megawatt (MW) gas-fired power station near Komaragiri village in Kakinada, a port city in Andhra Pradesh which is owned an operated by [[Spectrum Power Generation]].<ref>Spectrum Power Generation, [http://spgl.co.in/about-us.html"About Us"], Spectrum Power Generation website, accessed February 2012.</ref> A planned 1300 MW expansion plan was initially considered as a coal-fired project but is now being promoted as a gas-fired plant. |
− | |||
==Location== | ==Location== | ||
The map below shows the location of the plant. | The map below shows the location of the plant. | ||
Line 6: | Line 5: | ||
==Background== | ==Background== | ||
− | |||
− | |||
− | |||
− | |||
A February 2009 Ministry of Coal document indicated that Spectrum Power Generation were considering a second coal-based phase at the site of their existing plant. Stage II of the plant, the document stated, could be a 1,320 megawatt plant comprising two 660MW generating units. Coal for the project is indicated as being sought from [[Mahanadi Coalfields Limited]], a [[Coal India]] subsidiary.<ref>Ministry of Coal, [http://www.google.com/url?sa=t&rct=j&q=sheshadri%20power%20%26%20infrastructure&source=web&cd=4&ved=0CD4QFjAD&url=http%3A%2F%2Fcoal.nic.in%2Fcpdlist230209.pdf&ei=fLU5T6aRGY-srAfTr8ziCA&usg=AFQjCNGAVo9yYyIu_R43eoDlARJvAtSf1A&cad=rja "List of Thermal Power Plants..."], February 23, 2009, page 22.</ref> In July 2011 the project was still listed by the Ministry of Coal as a pending application.<ref>Ministry of Coal, [http://www.google.com/url?sa=t&rct=j&q=lovapalem%20power%20station&source=web&cd=2&ved=0CCoQFjAB&url=http%3A%2F%2Fcoal.nic.in%2Fcpd190811.pdf&ei=ybs5T8bkOs7NrQfRwMG8CA&usg=AFQjCNHvK8N34tqcvfGNjrPvlC-v6ktYhg&cad=rja "Pending application of SEBs up to 31st July, 2011"], Ministry of Coal, August 2011.</ref> | A February 2009 Ministry of Coal document indicated that Spectrum Power Generation were considering a second coal-based phase at the site of their existing plant. Stage II of the plant, the document stated, could be a 1,320 megawatt plant comprising two 660MW generating units. Coal for the project is indicated as being sought from [[Mahanadi Coalfields Limited]], a [[Coal India]] subsidiary.<ref>Ministry of Coal, [http://www.google.com/url?sa=t&rct=j&q=sheshadri%20power%20%26%20infrastructure&source=web&cd=4&ved=0CD4QFjAD&url=http%3A%2F%2Fcoal.nic.in%2Fcpdlist230209.pdf&ei=fLU5T6aRGY-srAfTr8ziCA&usg=AFQjCNGAVo9yYyIu_R43eoDlARJvAtSf1A&cad=rja "List of Thermal Power Plants..."], February 23, 2009, page 22.</ref> In July 2011 the project was still listed by the Ministry of Coal as a pending application.<ref>Ministry of Coal, [http://www.google.com/url?sa=t&rct=j&q=lovapalem%20power%20station&source=web&cd=2&ved=0CCoQFjAB&url=http%3A%2F%2Fcoal.nic.in%2Fcpd190811.pdf&ei=ybs5T8bkOs7NrQfRwMG8CA&usg=AFQjCNHvK8N34tqcvfGNjrPvlC-v6ktYhg&cad=rja "Pending application of SEBs up to 31st July, 2011"], Ministry of Coal, August 2011.</ref> | ||
Revision as of 18:31, 10 February 2014
{{#badges: CoalSwarm|Navbar-Indiacoal}} Uppada power station is an existing 208-megawatt (MW) gas-fired power station near Komaragiri village in Kakinada, a port city in Andhra Pradesh which is owned an operated by Spectrum Power Generation.[1] A planned 1300 MW expansion plan was initially considered as a coal-fired project but is now being promoted as a gas-fired plant.
Contents
Location
The map below shows the location of the plant.
Background
A February 2009 Ministry of Coal document indicated that Spectrum Power Generation were considering a second coal-based phase at the site of their existing plant. Stage II of the plant, the document stated, could be a 1,320 megawatt plant comprising two 660MW generating units. Coal for the project is indicated as being sought from Mahanadi Coalfields Limited, a Coal India subsidiary.[2] In July 2011 the project was still listed by the Ministry of Coal as a pending application.[3]
A 2010 document by Spectrum Power Generation indicates that the proposed project is now planned to be a 1,350 MW gas-fired project.[4] On its website, Spectrum also refers to the project as being a gas-fired power station.[5]
Project Details
Sponsor: Spectrum Power Generation
Location: Komaragiri village in Kakinada, Andhra Pradesh, India
Coordinates: 17.0587, 82.3097 (exact)
Status: No longer being pursued as a coal project
Nameplate capacity: 1320 (coal) (1350 (Gas) MW
Type:
Projected in service:
Coal Type:
Coal Source:
Estimated annual CO2:
Source of financing:
Resources and articles
Related SourceWatch articles
References
- ↑ Spectrum Power Generation, "About Us", Spectrum Power Generation website, accessed February 2012.
- ↑ Ministry of Coal, "List of Thermal Power Plants...", February 23, 2009, page 22.
- ↑ Ministry of Coal, "Pending application of SEBs up to 31st July, 2011", Ministry of Coal, August 2011.
- ↑ Spectrum Power Generation, "350+ MW Natural Gas based CCPP Bid Enquiry Document for MPE Contract", EQ International, undated but approximately March 2010, page 3.
- ↑ Spectrum Power Generation, "Capacity Expansion Considerations- 1350 mw gas based expansion project", Spectrum Power Generation website, accessed February 2012.