Difference between revisions of "Akita power station"
(construction delay) |
Bob Burton (talk | contribs) m (→Background: format) |
||
Line 14: | Line 14: | ||
In September 2018 Kiko Network stated that the assessment process for both units was ongoing and that commissioning was scheduled for 2024.<ref>[https://www.kikonet.org/wp/wp-content/uploads/2018/11/Report_Japan-Coal-Phase-Out_EG.pdf Japan Coal Phase-Out], Kiko Network, November 2018</ref> | In September 2018 Kiko Network stated that the assessment process for both units was ongoing and that commissioning was scheduled for 2024.<ref>[https://www.kikonet.org/wp/wp-content/uploads/2018/11/Report_Japan-Coal-Phase-Out_EG.pdf Japan Coal Phase-Out], Kiko Network, November 2018</ref> | ||
− | In March 2019 it was reported that Marubeni Corporation told the Nikkei media company that it would not proceed with the proposed Akita coal plant. According to The Australian Financial Review, Marubeni has yet to formally announce the decision because it is still trying to convince its joint-venture development partner, Kansai Electric Power, to also abandon the project.<ref>[https://www.afr.com/news/power-plant-cancellations-in-japan-buoy-anticoal-push-20190314-h1cd04 "Power plant cancellations in Japan buoy anti-coal push,"] The Australian Financial Review, March 14, 2019</ref> In August 2019 a spokesman for Kansai Electric Power announced that construction would not begin in August 2019 as planned and that no new construction schedule had been set.<ref>[http://ieefa.org/japanese-firms-delay-construction-of-1-3gw-coal-plant/ Japanese firms delay construction of 1.3GW coal plant], IEEFA, Aug. 15, 2019</ref> | + | In March 2019 it was reported that Marubeni Corporation told the Nikkei media company that it would not proceed with the proposed Akita coal plant. According to ''The Australian Financial Review'', Marubeni has yet to formally announce the decision because it is still trying to convince its joint-venture development partner, Kansai Electric Power, to also abandon the project.<ref>[https://www.afr.com/news/power-plant-cancellations-in-japan-buoy-anticoal-push-20190314-h1cd04 "Power plant cancellations in Japan buoy anti-coal push,"] ''The Australian Financial Review'', March 14, 2019</ref> In August 2019 a spokesman for Kansai Electric Power announced that construction would not begin in August 2019 as planned and that no new construction schedule had been set.<ref>[http://ieefa.org/japanese-firms-delay-construction-of-1-3gw-coal-plant/ Japanese firms delay construction of 1.3GW coal plant], IEEFA, Aug. 15, 2019</ref> |
==Project Details== | ==Project Details== |
Revision as of 00:21, 19 August 2019
{{#badges:CoalSwarm|Navbar-Japanandcoal}} Akita power station is a proposed 1,300-megawatt (MW) coal-fired power station in Akita, Japan.
Contents
Location
The map below shows Akita prefecture, the approximate location where the plant would be built, in the Tōhoku region of northern Honshu, the main island of Japan.
Background
In March 2015 Kansai Electric Power and Marubeni Corp. informed Akita prefecture of their plans to build a new 1,300 MW coal-fired power station in an industrial park on Akita's northern coast. Kansai Electric plans to use the Akita project to supply electricity to customers in Tokyo. Construction is slated to begin around 2019 and commercial operations around 2025.[1]
The EIA was submitted in September 2015.[2]
In November 2015 Japan’s environment minister Tamayo Marukawa said she won’t support the project, and that Japan should develop a plan to meet its stated goal of reducing greenhouse gas emissions 35 percent from 2013 levels by 2030.[3][4]
In September 2018 Kiko Network stated that the assessment process for both units was ongoing and that commissioning was scheduled for 2024.[5]
In March 2019 it was reported that Marubeni Corporation told the Nikkei media company that it would not proceed with the proposed Akita coal plant. According to The Australian Financial Review, Marubeni has yet to formally announce the decision because it is still trying to convince its joint-venture development partner, Kansai Electric Power, to also abandon the project.[6] In August 2019 a spokesman for Kansai Electric Power announced that construction would not begin in August 2019 as planned and that no new construction schedule had been set.[7]
Project Details
- Sponsor: Kansai Electric Power and Marubeni Corp.
- Location: Akita Prefecture, Honshu Province, Japan
- Coordinates: 39.718611, 140.1025 (approximate)
- Status: Pre-permit development
- Capacity: 1,300 MW
- Type: Ultra-supercritical
- Start date: 2024
- Coal Type:
- Coal Source:
- Source of financing:
- Permits and applications: EIA, Honshu Province, 2015/09/25
Articles and Resources
References
- ↑ Mari Iwata, "Japan Continues to Re-Embrace Coal:Lack of nuclear energy prompts return to coal as other countries move away from ‘dirty’ fuel source," WSJ, March 12, 2015
- ↑ EIA, Honshu Province, 2015/09/25
- ↑ "Japan Minister Says She Won't Support 2 Coal Power Projects," Bloomberg, Nov 12, 2015
- ↑ "秋田港発電所(仮称)建設計画に係る計画段階環境配慮書に対する環境大臣意見の提出について(お知らせ)," Japan MEP, Nov 13, 2015
- ↑ Japan Coal Phase-Out, Kiko Network, November 2018
- ↑ "Power plant cancellations in Japan buoy anti-coal push," The Australian Financial Review, March 14, 2019
- ↑ Japanese firms delay construction of 1.3GW coal plant, IEEFA, Aug. 15, 2019