Nasik RattanIndia Thermal Power Project
{{#Badges:CoalSwarm|navbar-Indiacoal}}Nasik Thermal Power Project is a proposed 2700 megawatt (MW) coal-fired power station in Maharashtra, India.
Contents
Location
The undated satellite photo below shows construction activity at the site, which is located about 6 km east of Sinnar in Nasik district.
Background
The power station is being developed in two phases by Indiabulls Power (later known as RattanIndia Nasik Power) in Sinnar, Nasik district. Phase I would be 1350 MW (5 x 270 MW) and Phase II: 1350 MW (5 x 270 MW).
In 2011 the company stated that "coal linkage has been granted and letters of assurance from South Eastern Coalfields Ltd. (SECL), Western Coalfields Ltd. (WCL) and Mahanadi Coalfields Ltd. (MCL) have been issued."[1] The company also stated that the project had achieved financial closure and that "construction is in full swing."[2]
According to the September 2013 report of the Central Electricity Authority, construction had slipped significantly, with estimated completion of Phase I expected expected during 2014 and 2015. As for Phase II, the report no longer lists the project as under construction.[3][3]
According to the February 2015 report of the Central Electricity Authority, Unit 1 was commissioned in 2014, and Unit 2 in 2015.[4] However, in November 2014 it was reported that the full phase I of the Nashik plant was ready for commissioning but had not done so due to want of coal. Phase II was on hold.[5] In July 2015 the MInistry of Power said units 3-5 are planned for commercial operation in 2017-2018. Phase II is planned for India's 13th plan (2018-2023).[6]
Project Details
Sponsor: RattanIndia Nasik Power (formerly Indiabulls Power)
Location: Sinnar village, Nasik district, Maharashtra
Coordinates: 19.8666594, 74.0817493 (exact)
Status:
- Phase I, Unit 1-2: Operating (2014-5)
- Phase I, Units 3-5: Construction
- Phase II, Units 1-5: Permitted
Nameplate capacity:
- Phase I: 1350 MW (5 x 270 MW)
- Phase II: 1350 MW (5 x 270 MW)
Type:
Projected in service:
- Phase I, Unit 3: 2017
- Phase I, Unit 4: 2017
- Phase I, Unit 5: 2018
- Phase II: 2018-2023
Coal Type:
Coal Source: South Eastern Coalfields Limited, Western Coalfields Limited and Mahanadi Coalfields Limited
Estimated annual CO2:
Source of financing:
Permits and applications:
- Phase I, Units: 1-5: Environmental Clearance, India MoEF, July 28, 2010
- Phase II, Units 1-5: Environmental Clearance, India MoEF, August 5, 2011
Resources
References
- ↑ Indiabulls Power, "Nasik Thermal Power Project", Indiabulls Power website, accessed November 2011.
- ↑ "Robust results for Indiabulls Power in FY 2011-12," Indiabulls press release, April 28, 2012
- ↑ Jump up to: 3.0 3.1 Monthly Report on Broad Status of Thermal Power Projects in the Country, Central Electricity Authority, February 2014 Cite error: Invalid
<ref>
tag; name "broad" defined multiple times with different content - ↑ Broad Status Report, India Central Electrical Authority, February 2015
- ↑ "Rattan India Power to bid for coal blocks to revive units," Economic Times, Nov 9, 2014
- ↑ "Supply of coal to Power Plants," India Ministry of Power, July 23, 2015