{{#badges: CoalSwarm|Navbar-Indiacoal}} Bander power station, also known as Pynampuram Thermal Power Project, is a 1320-megawatt (MW) coal-fired power station in Andhra Pradesh, India.

Location

The map below shows Painampuram village, the approximate location where the plant would be built.

Background

Bander power station is a proposed coal-fired power station in Andhra Pradesh, to be developed in three phases by Thermal Powertech Corporation. Phase I (2 units of 660 MW) and II (one unit of 660 MW) received an environmental permit in 2009,[1] and Phase III (one unit of 660 MW) a terms of reference in 2010 for applying for one.[2]

As of 2014 Thermal Powertech Corporation's website only mentions the first phase (1320 MW). It appears that Phases II and III have been abandoned.[3] Phase I is under construction,[4] and planned for operation in 2015.[5]

Unit 1 went into commercial operation in April 2015, and unit 2 in September 2015.[6][7]

Project Details

Sponsor: Thermal Powertech Corporation
Location: Painampuram village, Mutukur mandal, Nellore district, Andhra Pradesh
Coordinates: 14.351195, 80.143086 (exact)
Status:

  • Phase I, Units 1-2: Operating
  • Phase II: Cancelled
  • Phase III: Cancelled

Capacity:

  • Phase I: 1320 MW (Units 1&2: 660 MW)
  • Phase II: 660 MW
  • Phase III: 660 MW

Type: Supercritical
Projected in service:

  • Phase I: 2015

Coal Type:
Coal Source: Imported coal will be transported by ship to Krishnapatnam Port. Indigenous coal will be brought by rail from Ib Valley/Talcher to Paradip/ Dhamra Port and then transported by sea to Krishnapatnam Port[3]
Estimated annual CO2: 798,350 tons[8]
Source of financing:
Permits and applications:

Articles and resources

References

  1. Environmental clearance, India MoEF, Nov 4, 2009.
  2. Terms of Reference, India MoEF, Mar 12, 2010.
  3. Jump up to: 3.0 3.1 "Project Details," Thermal Power Corporation website, accessed January 2012
  4. "THERMAL PROJECTS TARGETED FOR COMMISSIONING DURING 12TH PLAN," Data Insights, Feb 2014.
  5. "Monthly Report," CEA, November 2014
  6. "Sembcorp's first coal-fired plant in India starts operations," The Edge Markets, Sep 14, 2015
  7. ""Monthly Report," CEA, April 2015
  8. For estimation method, see Estimating carbon dioxide emissions for proposed coal plants in India