Pudimadaka Ultra Mega Power Project
{{#badges: CoalSwarm|Navbar-Indiacoal}} Pudimadaka Ultra Mega Power Project is a proposed 4,000-megawatt coal-fired power station by NTPC in Andhra Pradesh, India.
Contents
Location
The map below shows the location of Pudimadaka village near Anakapalle, but not the exact location of the project.
Background
NTPC and the government of Andhra Pradesh signed a draft power purchase agreement for this project in early 2011, but subsequently the company made no progress on land acquisition.[1]
In January 2014 project sponsor NTPC said it was planning on fast-tracking the project. The project was initially to use domestic coal, but facing difficulty in securing a coal linkage, it may use imported coal. NTPC is awaiting land clearance from the state government, and will then seek the necessary permits, after which it will take an estimated 42 months to implement the five 800 MW units.[2]
In September 2014, The Hindu reported that NTPC will receive fast-track status for the project. 1200 acres were reported to have been allotted the project. According to the report, Chief Minister N. Chandrababu Naidu has instructed officials to accord all clearances without delay. The next step in the process will be land acquisition, followed by geotechnical investigation, topography, and environmental assessment studies, and then public hearings.[1]
A terms of reference was issued for the project in February 2015.[3] A public hearing on the plant was held in August 2015. An estimated one thousand local people attended, many of them opposing the plant based on its pollution effects.[4]
Project Details
Sponsor: NTPC
Location: Pudimadaka village, Achutapuram mandel, Visakhapatnam district, Andhra Pradesh
Coordinates: 17.492713, 83.002767 (approximate)
Status: Pre-permit development
Nameplate capacity:
- Unit 1: 800MW
- Unit 2: 800MW
- Unit 3: 800MW
- Unit 4: 800MW
- Unit 5: 800MW
Type: Supercritical
Projected in service:
Coal Type:
Coal Source: Imported coal, estimated at 19.8 million tonnes per annum[1]
Estimated annual CO2:
Source of financing:
Permit and applications: "Terms of Reference," India MoEF, Feb. 25, 2015
Articles and resources
References
- ↑ Jump up to: 1.0 1.1 1.2 Santosh Patnaik, "NTPC Pudimadaka power plant to get fast-track status," The Hindu, September 9, 2014
- ↑ "NTPC seeks to fast track Pudimadaka project," The Hindu Online, Jan 29, 2014.
- ↑ "Terms of Reference," India MoEF, Feb. 25, 2015
- ↑ "Public hearing for NTPC 4,000 MW project held amid protests," The Hindu, Aug 12, 2015
Related SourceWatch articles
External resources
External articles
- "NTPC's Pudimadaka plant to get fast-track clearances," The Hindu, January 7, 2011
- V. Rishi Kumar, "NTPC to take up another mega project in South," The Hindu Business Line, January 23, 2012