{{#badges:CoalSwarm|Navbar-Chinacoal}}Wulanhaote Hengwang power station (乌拉特后旗恒旺热电厂) is a proposed 400-megawatt (MW) coal-fired power plant in Inner Mongolia Autonomous Region, China.
Contents
Location
The map below shows the location of Urad Rear Banner, the approximate location where the plant would be built in Hinggan (Xing'an Meng) Prefecture, Inner Mongolia Autonomous Region.
Loading map...
Background on Project
In 2011 Inner Mongolia Wulahot Hengwang Heat & Electricity Generation issued tender notice to build a single-unit coal-fired power plant with a total planned capacity of 400 MW in Inner Mongolia Autonomous Region.[1]
However, there has been no news of the plans since 2012,[2] and the project appears to be abandoned.
Project Details
- Sponsor: Inner Mongolia Wulahot Hengwang Heat & Electricity Generation
- Parent company:
- Location: Urad Rear Banner, Bayannur Prefecture, Inner Mongolia Autonomous Region, China
- Coordinates: 41.083333, 107.066667 (approximate)
- Status: Cancelled
- Gross capacity: 400 MW (Units 1 & 2: 200 MW)
- Type: Subcritical
- Projected in service:
- Coal type:
- Coal source:
- Source of financing: