According to the 2010-2011 annual report of Tata Power, "All statutory clearances required to start the 1,600 MW Coastal Maharashtra Project are in place. Disbursement of compensation to landowners is in progress by Raigad District Authorities and above 50% of private land has been acquired till date." The company also reports that it has secured a fresh water allocation from the Maharashtra Industrial Development Corporation (MIDC). Compensation to landowners began in August 2010. "Economic options for coal logistics are under evaluation."<ref name=AR>[http://bit.ly/z4L2zA "Growth Plans,"] Tata Power 2010-2011 Annual Report</ref>
'''==Location==The map below shows the village of Shahapur, but not the exact location of the project:'''
{{#display_point:|Shahapur, Maharashtra|width=500|height=400|type=normal|zoom=8}}