MSPGCL states on its website that the addition of 1960MW at the Koradi Thermal Power Station is currently under construction. The expansion would comprise three 600MW units referred to as Units 8, 9 and 10. Unit 8 is projected to be commissioned by December 2013 followed by Unit 9 by June 2014 and Unit 10 by Dec. 2014.<ref>Maharashtra State Power Generation Company, [http://www.mahagenco.in/Ongoing-projects_english.pdf "Information on Mahagenco's Power Projects: Ongoing Thermal Power Projects – 4730 MW"], Maharashtra State Power Generation Company website, August 26, 2011.</ref>
==Location==
The map below shows the village of Koradi, but not the exact location of the project:
{{#display_point:|Koradi, Maharashtra|width=500|height=400|type=normal|zoom=8}}
==Project Details==
'''Sponsor:'''[[Maharashtra State Power Generation Company]] (MSPGCL)<br>'''Location:''' Koradi village, Nagpur district, Maharashtra state, India<br>
'''Coordinates:''' <br>
'''Status:'''Under construction<br>'''Nameplate capacity:''' 1040 MW existing, plus 1960 MW expansion<br>
'''Type:''' <br>