==Background==
In February 2010, it was reported that sponsor [[GMR Group]] would begin construction on the stationin the following months,<ref>[http://bit.ly/ABjb6E "GMR Chhattisgarh Power Project,"] GMR Energy, accessed February 2012</ref> in the following months, with the two units commissioned within 45 months and 50 months respectively, around 2014.<ref name=GMR>GMR Group, [http://www.gmrgroup.in/Energy/GMR_Chhattisgarh_Power_Project.html "GMR Chhattisgarh Power Project"], GMR Group website, accessed November 2011.</ref><ref>[http://bit.ly/zg2G88 "Work to begin by March on GMR's Chhattisgarh project,"] ConstructionUpdate.com, February 2010</ref>
==Banks withhold funds==