In October 2014 NMDC said it had put the Gonda project on hold, saying the project was not viable as there had been no progress on a location for the plant. NMDC said the project may be taken up at a later date, or cancelled.<ref>[http://articles.economictimes.indiatimes.com/2014-10-06/news/54691571_1_iedcl-nmdc-power-ltd-power-plant "NMDC puts Uttar Pradesh's Gonda power plant project on back burner,"] Economic Times, Oct 6, 2014</ref>
 
With no further news on the project as of October 2016, it appears to be abandoned.
==Project Details==
*'''Location:''' Turkadih village, Mankapur taluk, Gonda district, Uttar Pradesh
*'''Coordinates:''' 27.03, 82.23 (approximate)
*'''Status:''' ShelvedCancelled
*'''Capacity:'''
**Unit 1: 250 MW