In March 2016 it was reported that although units 1-2 at the plant were idled due to lack of demand, unit 3 would be commissioned that month.<ref>Ashish Roy, [http://timesofindia.indiatimes.com/city/nagpur/Two-units-idle-but-NTPC-will-start-3rd-one-at-Mouda/articleshow/51247385.cms "Two units idle, but NTPC will start 3rd one at Mouda,"] Times of India, Mar 4, 2016</ref> It was commissioned in May 2016.<ref>[http://www.greentechlead.com/power/bhel-commissions-660-mw-power-plant-maharashtra-30111 "BHEL commissions 660 MW power plant in Maharashtra,"] greentechlead.com, May 14, 2016</ref>
Unit 4 was commissioned in March 2017.<ref>[http://cea.nic.in/reports/monthly/broadstatus/2017/broad_status-03.pdf "Broad Status Report,"] India Central Electrical Authority, March 2017</ref>
==Project Details==
'''Coordinates:''' 21.1807403, 79.3965411 (exact)<br>
'''Status:'''
*Units 1-34: Operating*Unit 4: Construction
'''Capacity:'''
*Phase I: 1000 MW (Units 1 & 2: 500 MW)