In December 2016, the two units of the plant were projected to come online in February and April of 2017.<ref>[http://www.cea.nic.in/reports/monthly/broadstatus/2016/broad_status-12.pdf "Monthly Report on Broad Status of Thermal Power Projects in the Country,"] Government of India Ministry of Power, December 2016</ref> As of March 2017, the commissioning dates had slipped to June and September of 2017.<ref>[http://cea.nic.in/reports/monthly/broadstatus/2017/broad_status-03.pdf "Broad Status Report,"] India Central Electrical Authority, March 2017</ref>
Unit 1 was commissioned in September 2017. Unit 2 is planned for December 2017.<ref>[http://www.cea.nic.in/reports/monthly/broadstatus/2017/broad_status-09.pdf “Broad Status of Thermal Power Projects in the Country,”] India Ministry of Power, Sep 2017</ref>
==Project Details==
'''Location:''' Nardana MIDC area, Vaghode village, Shindkheda taluk, Dhule district, Maharashtra<br>
'''Coordinates:''' 21.152106, 74.8539841 (exact)<br>
'''Status:''' Operating (Unit 1), Construction(Unit 2)<br>'''Start date:''' 2017<br>
'''Capacity:''' 300 MW (2 x 150 MW)<br>
'''Type:''' <br>'''Projected in service:''' [[Subcritical]]<br>
'''Coal Source:''' blended coal from India and Indonesia (from Surat or Dahej) - 5000 Kcal/Kg<ref>[http://www.shirpurpower.com/MasterPage/Fuel.php "Fuel,"] Shirpur Power website, accessed April 2014</ref><br>
'''Estimated annual CO<sub>2</sub>:''' <br>
'''Source of financing:''' <br>
'''Source of financing:'''<br>
'''Permits and applications:''' [http://bit.ly/1lNWJS5 Environmental Clearance,] India MoEF, November 25, 2010