In December 2016, the two units of the plant were projected to come online in February and April of 2017.<ref>[http://www.cea.nic.in/reports/monthly/broadstatus/2016/broad_status-12.pdf "Monthly Report on Broad Status of Thermal Power Projects in the Country,"] Government of India Ministry of Power, December 2016</ref> As of March 2017, the commissioning dates had slipped to June and September of 2017.<ref>[http://cea.nic.in/reports/monthly/broadstatus/2017/broad_status-03.pdf "Broad Status Report,"] India Central Electrical Authority, March 2017</ref>
Unit 1 was commissioned in September 2017. Unit 2 is planned for December 2017March 2018.<ref>[http://www.cea.nic.in/reports/monthly/broadstatus/2017/broad_status-0910.pdf “Broad "Broad Status of Thermal Power Projects in the CountryReport,”"] India Ministry of PowerCentral Electrical Authority, Sep October 2017</ref>