Difference between revisions of "Sakhalin GRES-2 power station"

From SourceWatch
Jump to navigation Jump to search
(Phase II and Phase III cancelled)
(Units 1-2 commissioned)
 
Line 1: Line 1:
{{#badges:CoalSwarm|Navbar-Russiacoal}}'''Sakhalin GRES-2 power station''' is a 360-megawatt (MW) proposed coal-fired power plant in Sakhalin province, Russia.
+
{{#badges:CoalSwarm|Navbar-Russiacoal}}'''Sakhalin GRES-2 power station''' is a 120-megawatt (MW) proposed coal-fired power plant in Sakhalin province, Russia. A further 240 MW was proposed but cancelled.
  
 
==Location==  
 
==Location==  
Line 12: Line 12:
 
Construction on Phase 1 began in March 2015, with [[Mosenergo]] as the construction contractor.<ref name=skr>[http://skr.su/news/245166 Строительство Сахалинской ГРЭС-2], 2 Mar. 2015.</ref><ref name=interfax>[http://www.interfax.ru/russia/414725 Окончание строительства Сахалинской ГРЭС-2 могут сдвинуть на год], Interfax, 22 Dec. 2014.</ref> The plant's chimney was completed in July 2016.<ref>[http://www.rushydro.ru/press/news/101096.html На Сахалинской ГРЭС-2 завершили возведение ствола дымовой трубы], RusHydro press release, 11 July 2016.</ref>  
 
Construction on Phase 1 began in March 2015, with [[Mosenergo]] as the construction contractor.<ref name=skr>[http://skr.su/news/245166 Строительство Сахалинской ГРЭС-2], 2 Mar. 2015.</ref><ref name=interfax>[http://www.interfax.ru/russia/414725 Окончание строительства Сахалинской ГРЭС-2 могут сдвинуть на год], Interfax, 22 Dec. 2014.</ref> The plant's chimney was completed in July 2016.<ref>[http://www.rushydro.ru/press/news/101096.html На Сахалинской ГРЭС-2 завершили возведение ствола дымовой трубы], RusHydro press release, 11 July 2016.</ref>  
  
As of August 2016, completion was scheduled for the fourth quarter of 2017,<ref>[https://ria.ru/economy/20160812/1474260075.html Строительство Сахалинской ГРЭС-2 планируют завершить к концу 2017 года], RIA Novosti, 12 Aug. 2016.</ref> later pushed to 2018.<ref>[https://sakhalin.info/sakhgres/140077 "Первые холостые испытания СахГРЭС-2 перенесены на начало 2018 года,"] Sakhalin Indo, Oct 6, 2017</ref> As of March 2018, construction on Phase 1 was 70% complete, and completion was scheduled for the end of 2018.<ref>[https://otr-online.ru/news/k-zapusku-gotovitsya-99727.html К запуску готовится Сахалинская ГРЭС-2], Общественное телевидение России, 5 Mar. 2018.</ref> In October 2018 RusHydro announced that the plant would be finished in 2019.<ref>[https://ria.ru/teplo/20181011/1530483244.html Русгидро не переносит пуски с Сахалинской ГРЭС-2 и Совгаванской ТЭЦ], ria.ru, Oct. 18, 2018</ref>
+
As of August 2016, completion was scheduled for the fourth quarter of 2017,<ref>[https://ria.ru/economy/20160812/1474260075.html Строительство Сахалинской ГРЭС-2 планируют завершить к концу 2017 года], RIA Novosti, 12 Aug. 2016.</ref> later pushed to 2018.<ref>[https://sakhalin.info/sakhgres/140077 "Первые холостые испытания СахГРЭС-2 перенесены на начало 2018 года,"] Sakhalin Indo, Oct 6, 2017</ref> As of March 2018, construction on Phase 1 was 70% complete, and completion was scheduled for the end of 2018.<ref>[https://otr-online.ru/news/k-zapusku-gotovitsya-99727.html К запуску готовится Сахалинская ГРЭС-2], Общественное телевидение России, 5 Mar. 2018.</ref> In October 2018 RusHydro announced that the plant would be finished in 2019.<ref>[https://ria.ru/teplo/20181011/1530483244.html Русгидро не переносит пуски с Сахалинской ГРЭС-2 и Совгаванской ТЭЦ], ria.ru, Oct. 18, 2018</ref> In November 2019 the two 60-MW units were commissioned.<ref>[https://ria.ru/20191125/1561541178.html Сахалинскую ГРЭС-2 ввели в эксплуатацию], ria.ru, Nov. 25, 2019</ref>
  
 
As of June 2019 there has been no further news about Phase II or Phase III of the project and they appear to be cancelled.
 
As of June 2019 there has been no further news about Phase II or Phase III of the project and they appear to be cancelled.
Line 21: Line 21:
 
*'''Location:''' Ilyinskoye village, Tomarinsky district, Sakhalin province, Russia
 
*'''Location:''' Ilyinskoye village, Tomarinsky district, Sakhalin province, Russia
 
*'''Coordinates:''' 48.053759, 142.187548 (exact)
 
*'''Coordinates:''' 48.053759, 142.187548 (exact)
*'''Status:''' Construction (Units 1-2); Cancelled (Units 3-6)
+
*'''Status:''' Operating (Units 1-2); Cancelled (Units 3-6)
 
*'''Gross Capacity:''' 120 MW (2 x 60 MW)
 
*'''Gross Capacity:''' 120 MW (2 x 60 MW)
 
*'''Type:''' [[Subcritical]]
 
*'''Type:''' [[Subcritical]]
*'''Projected in service:''' 2019 (Units 1-2); TBD (Units 3-6)
+
*'''In service:''' Units 1-2: 2019
 
*'''Coal Type:''' Lignite<ref name=skr/>
 
*'''Coal Type:''' Lignite<ref name=skr/>
 
*'''Coal Source:''' Solntsevskoye coal mine, Sakhalin, Russia<ref name=sakhalinmedia/>
 
*'''Coal Source:''' Solntsevskoye coal mine, Sakhalin, Russia<ref name=sakhalinmedia/>
Line 38: Line 38:
 
===External resources===
 
===External resources===
  
 +
[[Category: Existing coal plants in Russia]]
 +
[[Category: Existing coal plants in Europe]]
 
[[Category: Proposed coal plants in Russia]]
 
[[Category: Proposed coal plants in Russia]]
 
[[Category: Proposed coal plants in Europe]]
 
[[Category: Proposed coal plants in Europe]]
 
[[Category: Energy]]
 
[[Category: Energy]]
 
[[Category: Russia]]
 
[[Category: Russia]]

Latest revision as of 17:25, 20 December 2019

{{#badges:CoalSwarm|Navbar-Russiacoal}}Sakhalin GRES-2 power station is a 120-megawatt (MW) proposed coal-fired power plant in Sakhalin province, Russia. A further 240 MW was proposed but cancelled.

Location

The map below shows the location of the project, according to Wikimapia, near the village of Ilyinskoye, Tomarinsky district, Sakhalin province.[1]

Background on Plant

The firm Sakhalinenergo — a subsidiary of RAO Energy System of East, which is itself a subsidiary of RusHydro — is currently engaged in a project to build a 360-MW coal-fired power plant 5 km from the village of Ilyinskoye, on the southwest coast of Sakhalin. The plant is planned to replace the aging Sakhalin GRES-1 power station — a separate, 252-MW coal-fired power plant, also owned by Sakhalinenergo, which is located on the east coast of Sakhalin, about 120 km to the northeast.[2][3][4][5]

The first of the three phases of Sakhalin GRES-2, totaling 120-MW, was originally planned to begin construction in mid-2014 and be completed in 2016. Ownership of the plant will be transferred to a new RusHydro subsidiary, JSC Sakhalin GRES-2, at some future date. It is unclear when the other two phases would be built.[2][6]

Construction on Phase 1 began in March 2015, with Mosenergo as the construction contractor.[7][8] The plant's chimney was completed in July 2016.[9]

As of August 2016, completion was scheduled for the fourth quarter of 2017,[10] later pushed to 2018.[11] As of March 2018, construction on Phase 1 was 70% complete, and completion was scheduled for the end of 2018.[12] In October 2018 RusHydro announced that the plant would be finished in 2019.[13] In November 2019 the two 60-MW units were commissioned.[14]

As of June 2019 there has been no further news about Phase II or Phase III of the project and they appear to be cancelled.

Project Details

  • Sponsor: Sakhalinenergo
  • Parent company: RusHydro
  • Location: Ilyinskoye village, Tomarinsky district, Sakhalin province, Russia
  • Coordinates: 48.053759, 142.187548 (exact)
  • Status: Operating (Units 1-2); Cancelled (Units 3-6)
  • Gross Capacity: 120 MW (2 x 60 MW)
  • Type: Subcritical
  • In service: Units 1-2: 2019
  • Coal Type: Lignite[7]
  • Coal Source: Solntsevskoye coal mine, Sakhalin, Russia[2]
  • Source of financing: Sberbank[15]

Articles and resources

References

  1. Sakhalin TPP-2 (Construction site), Wikimapia, accessed July 2016.
  2. Jump up to: 2.0 2.1 2.2 Сахалинскую ГРЭС-2 будут строить в Томаринском районе, SakhalinMedia, Mar. 4, 2013.
  3. RusHydro 2012 Annual Report, pp. 12-15.
  4. RusHydro Earmarks RUB 360.868 bln for 2014-2018 Investment Program, Peretok, Feb. 24, 2014.
  5. Сахалинская ГРЭС-2, Wikipedia (Russian), accessed June 2018.
  6. Ж/д ветка свяжет Сахалинскую ГРЭС-2 и действующую железную дорогу, SakhalinMedia, Nov. 15, 2013.
  7. Jump up to: 7.0 7.1 Строительство Сахалинской ГРЭС-2, 2 Mar. 2015.
  8. Окончание строительства Сахалинской ГРЭС-2 могут сдвинуть на год, Interfax, 22 Dec. 2014.
  9. На Сахалинской ГРЭС-2 завершили возведение ствола дымовой трубы, RusHydro press release, 11 July 2016.
  10. Строительство Сахалинской ГРЭС-2 планируют завершить к концу 2017 года, RIA Novosti, 12 Aug. 2016.
  11. "Первые холостые испытания СахГРЭС-2 перенесены на начало 2018 года," Sakhalin Indo, Oct 6, 2017
  12. К запуску готовится Сахалинская ГРЭС-2, Общественное телевидение России, 5 Mar. 2018.
  13. Русгидро не переносит пуски с Сахалинской ГРЭС-2 и Совгаванской ТЭЦ, ria.ru, Oct. 18, 2018
  14. Сахалинскую ГРЭС-2 ввели в эксплуатацию, ria.ru, Nov. 25, 2019
  15. RusHydro, Sberbank Sign Banking Services Agreement for Power Plant Construction, Highbeam Business, Mar. 27, 2013.