{{#badges:CoalSwarm|Navbar-Brazilcoal}}The MPX Itaqui power project is a 360-megawatt (MW) coal-fired power station operated by Eneva (formerly MPX Energia) in São Luís de Maranhão, Brazil. Originally known as UTE Termomaranhão, the plant now goes by the official name UTE Porto do Itaqui.

Location

The photo below the project in São Luís de Maranhão

Background

Diferencial Energia, original developer of the Itaqui project, sold generation rights in March 2007 to Brazilian power holding company EDB [1], which in turn established a 50-50 partnership with Brazilian mining company MPX Mineração e Energia. MPX bought EDB's stake and assumed 100% ownership shortly after Brazil's October 2007 A-5 energy auction, in which the Itaqui plant won a contract to produce an annual average of 315 MW of power over a 15-year period.[2] In October 2012, the government environmental agency IBAMA (Instituto Brasileiro do Meio Ambiente) granted the plant its operating license[3], and in February 2013 the electrical agency ENEEL (Agência Nacional de Energia Elétrica) authorized the plant to begin commercial operations, with an installed capacity of 360 MW. [4]

Project Details

  • Sponsor: Eneva
  • Parent company: MPX Energia SA, E.ON
  • Location: São Luís de Maranhão, Brazil
  • Coordinates: -2.5873124, -44.3383527 (exact)
  • Status: Operating (2013)
  • Gross Capacity: 360 MW
  • Type: Subcritical
  • Projected in service:
  • Coal Type:
  • Coal Source:
  • Source of financing:

Articles and resources

References

  1. "EDB buys Maranhão project generation rights,", Business News Americas, April 11, 2007.
  2. "EDB sells stake in Maranhão thermo project,", Business News Americas, October 17, 2007.
  3. "UTE Itaqui obtém licença de operação emitida pelo Ibama,", Eneva media release, October 29, 2012.
  4. "UTE Itaqui, da MPX, inicia operação comercial,", Eneva media release, February 5, 2013.