{{#badges:CoalSwarm|Navbar-Chinacoal}}Huawei Hetian power station (华威和田发电有限公司二期热电联产项目) is a proposed 870-megawatt (MW) coal-fired power plant in Xinjiang Uyghur Autonomous Region, China.

Location

The undated satellite photo below shows the power station in Hotan (Hetian) Prefecture.

Background on Project

The power station consist of two phases. Phase I is a 2 x 135 MW power station in in Xinjiang Uyghur Autonomous Region.[1][2] As of 2014 the two units are under construction.[3]

Unit 1 began operating in 2015.[4]

Phase II is a coal-fired power plant with two units of 300 MW each.[5]

Project Details

  • Sponsor: Beijing Huawei Hetian Investment and Zhongmu Company
  • Parent company:
  • Location: Hotan (Hetian) Prefecture, Xinjiang Uyghur Autonomous Region, China
  • Coordinates: 37.167593, 79.905582 (exact)
  • Status: Operating (Unit 1), Construction (Unit 2), Announced (Units 3 and 4)
  • Gross capacity: 870 MW (Units 1 and 2: 135 MW; Units 3 and 4: 300 MW)
  • Type:
  • Projected in service: 2015 (Unit 1)
  • Coal type:
  • Coal source: