Anlong power station (安龙煤电化一体化产业基地热电联产) is a proposed 725-megawatt (MW) coal-fired power plant in Guizhou Province, China.
Contents
Location
The map below shows the location where the power station was first reported to begin construction near Lugoutang Village (鲁沟塘村), Puping Town, Anlong County, Qianxinan AP. As of April 2018, this appears to be the actual construction site.
The map below shows the location where the power station reportedly poured the first load of concrete near Xinzhai Village (新寨村), Puping Town, Anlong County, Qianxinan AP. However, as of April 2018 there have been no further developments.
Background on Project
Guizhou Anlong County Xinyu Resources Development Co is a local energy company who is the sponsor of a coal-fired power station of two 350 MW units in Anlong County. The proposed power plant will be a co-generation power plant, supplying electricity, heat and steam to a proposed chemical project. The power plant received a permit for construction from the provincial DRC in December 31, 2014. The construction reportedly started in November 2016 with a ceremony at Lugoutang Village, Puping Town, Anlong County.[1] [2]
In June 2017, a ceremony for celebrating the start of the construction was held again. [3] Between the two ceremonies, the sponsor of the power plant completed its preliminary design review.[4] The location also shifted to Xinzhai Village, Puping Town, Anlong County, 15 miles away by straight-line distance. The project would include a 25 MW back-up unit. The estimated investment in this power plant is ¥3.1 billion.[2]
However, satellite images from 2017-2018 show the construction site is at the first location, Lugoutang Village, Puping Town. As of April 2018, the construction is slowly ongoing.
Project Details
- Sponsor: Anlong Xinyu Resources Development Co.
- Parent company:
- Location: Lugoutang Village, Puping Town, Anlong County, Qianxinan AP Prefecture, Guizhou Province, China
- Coordinates: 25.29337, 105.388822 (exact)
- Status: Construction
- Gross capacity: 725 MW (Units 1-2: 350 MW, Unit 3: 25 MW)
- Type: Supercritical
- Projected in service:
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "贵州安龙煤电化一体化产业基地热电联产动力车间项目正式开工"中国能建东电二公司,] 2016-11-28
- ↑ 2.0 2.1 "总投资约31亿元 安龙煤电化产业基地热电联产项目开工," Anlong TV Station, 2016-11-25
- ↑ "贵州安龙煤电化一体化产业基地热电联产动力车间项目主厂房浇筑第一罐混凝土"中国能建东电二公司, 2017-06-21
- ↑ "安龙煤电化一体化产业基地热电联产动力车间项目初步设计评审会圆满结束"中国能建东电二公司贵州安龙项目部, 2017-06-22