Baoding Northwest Suburb power station
This article is part of the Coal Issues portal on SourceWatch, a project of Global Energy Monitor and the Center for Media and Democracy. See here for help on adding material to CoalSwarm. |
This article is part of the CoalSwarm coverage of China and coal | |
Sub-articles: | |
Baoding Northwest Suburb power station (深能保定发电公司) is a 350-megawatt (MW) coal-fired co-generation power station in Hebei Province, China.
Contents
Location
The undated satellite photo below shows the plant in Yaozhuang.
Background on Project
Shenzhen Energy has proposed a supercritical coal-fired co-generation power station of 700 MW for Yaozhuang in Mancheng District, Baoding. It is planned to supply heat in winter to Baoding City and be completed in 2017.[1][2]
The plant was permitted in 2015 and is under construction.[3]
Project postponed, then unit 1 revived
2017: Expansion postponed by government
In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[4]
Baoding Northwest Suburb power station Units 1-2 were among the postponed coal-burning units.[5]
September 2017: Suspension lifted on unit 1, continued on unit 2
After political negotiations, China's National Energy Administration (NEA) released an updated list of postponed and halted coal projects on September 26, 2017. The new list contained 151 units totaling 95 gigawatts (GW). Baoding Northwest Suburb power station Unit 1 was no longer on the list, while Unit 2 was, meaning only unit 2 is postponed.[6] For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.
Unit 1 began operating on December 31, 2017.[7]
Construction continues on Unit 2
Satellite photos for September 2017 and March 2018 show construction continuing on Unit 2.
Unit 2 was commissioned in September 2018.[8]
Project Details
- Sponsor: Shenzhen Energy
- Parent company: Shenzhen Energy
- Location: Yaozhuang, Mancheng District, Baoding Prefecture, Hebei Province, China
- Coordinates: 38.961835, 115.36719 (exact)
- Status: Operating
- Gross capacity: 700 MW (Units 1 & 2: 350 MW)
- Type: Supercritical
- Start date: 2017 (Unit 1), 2018 (Unit 2)
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "深能保定西北郊热电厂一期2×35万千瓦项目," 2015-05-08
- ↑ "深能保定西北郊热电厂一期2×350MW工程可研审查会在保定召开," 保定公司 作者, 2015-05-08
- ↑ "深圳能源集团股份有限公司关于投资建设保定西北郊热电厂一期2×35万千瓦超临界燃煤机组项目的公告," Sina, June 14, 2016
- ↑ "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
- ↑ "深能保定西北郊热电厂1号机组顺利通过168小时试运行," 深圳能源, 2018/1/3
- ↑ "深能保定西北郊热电厂2号机组通过168小时试运行," 中国电建, 2018/9/27