Broughton coal project

From SourceWatch
Jump to navigation Jump to search
Coalswarm badge.gif

This article is part of the Coal Issues portal on SourceWatch, a project of Global Energy Monitor and the Center for Media and Democracy. See here for help on adding material to CoalSwarm.

The Broughton coal project is a proposed opencast coal mine 27km north-west of the township of Nebo, 100km west south west of Mackay. This is in the Isaac Regional Council local government area of the Bowen Basin, Queensland Australia.[1]

The proposed mine would last 15 years and would require the diversion of the Suttor Developmental Road, a creek diversion and flood levees to be built. The product coal would be transported on a dedicated haul road to a new train loading facility connected to the Hail Creek rail branch. The coal is currently proposed to be exported through the Dalrymple Bay Coal Terminal, south of Mackay.[1]

The application is considered to be lapsed by Queensland Government.[1]

Location

The undated image below shows the approximate location of the proposed mine.

Loading map...

Coal Mine Background

On 13 September 2013, U & D Mining Industry (Australia) applied for an Environmental Authority permit. On 5 November 2013, the department notified U & D Mining Industry (Australia) that the application requires assessment by Environmental Impact Statement (EIS).[1]

The final Terms of Reference (TOR) for the EIS was issued to the proponent on 24 April 2015.

U & D Mining Industry (Australia) had until 24 April 2017 to prepare the EIS and submit it to the department for assessment. However, the EIS was not received by the due date. Consequently, the TOR for the project ceased to have effect and the TOR stage under Division 2 of the EP Act must be complied with again before the EIS for this project may be submitted.[1]

Project Details

  • Sponsor:
  • Parent Company: U & D Mining Industry (Australia)[1]
  • Location: 27km north-west of the township of Nebo 100km west south west of Mackay, Queensland Australia
  • GPS Coordinates: -21.547442, 148.474401 (approximate)
  • Status: Development (lapsed)[1]
  • Production Capacity: 3 mtpa[1]
  • Total Resource: 120.9 million tonnes[2]
  • Mineable Reserves:
  • Coal type:
  • Mine Size: 2,227 hectares[1]
  • Mine Type: opencast[1]
  • Start Year:
  • Source of Financing:

Articles and resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 Queensland Government, "Broughton Coal Project", Withdrawn or lapsed projects website, 15 October 2017.
  2. UD, "Broughton", U&D website, 2017.