CPI Minsheng power station (中电国际商丘民生热电公司) is a 700-megawatt (MW) coal-fired power plant in Henan Province, China.

Location

The undated satellite photo below shows the plant in Yangguanmiao Village of the Liangyuan District.

Loading map...

Background on Plant

China Power International has proposed the 2 x 350MW Minsheng coal plant in Yangguanmiao Village, Liangyuan District. The project was permitted in 2015.[1]

As of 2016 the power station is under construction.[2]

Unit 1 was commissioned in November 2018.[3] Unit 2 was commissioned in January 2019.[4]

Ownership

In July 2015, China Power Investment Corporation (CPI) and State Nuclear Power Technology Corporation (SNPTC) merged to become State Power Investment Corporation (国家电力投资集团), one of the five largest state-owned electricity producers in the People's Republic of China.[5]

Project Details

  • Sponsor: China Power International
  • Parent company: State Power Investment Corporation
  • Location: Yangguanmiao Village, Liangyuan District, Shangqiu Prefecture, Henan Province, China
  • Coordinates: 34.469434, 115.707177 (exact)
  • Status: Operating
  • Gross capacity: 700 MW (Units 1 & 2: 350 MW)
  • Type: Supercritical
  • Start year: 2018 (Unit 1), 2019 (Unit 2)
  • Coal type:
  • Coal source:
  • Source of financing: