CPI Shanxi Houma power station (中电投山西侯马发电厂) is a 600-megawatt (MW) coal-fired power plant in Shanxi Province, China.
Contents
Location
The undated satellite photo below shows the plant in Houma City, Linfen Prefecture, Shanxi Province.
Background on Plant
The six coal-fired units of Houma-1 power station, totaling 200 MW, were brought online between 1972 and 2004. Units 1-4 were retired in 2007, and units 5-6 in 2017. The plant was originally owned by CPI.[1]
Description of Expansion
Datong Coal Mining Group has proposed expanding the power station by 600 MW (2 x 300 MW), known as Shanxi Houma-2. The expansion began commercial operation in 2014.[2][3][4]
Ownership
In July 2015, China Power Investment Corporation (CPI) and State Nuclear Power Technology Corporation (SNPTC) merged to become State Power Investment Corporation (国家电力投资集团), one of the five largest state-owned electricity producers in the People's Republic of China.[5]
Project Details for Phase II Expansion
- Sponsor: SPIC Shanxi Electric Power Co, Ltd.
- Parent company: State Power Investment Corporation
- Location: Zhangshao village, Houma City, Linfen Prefecture, Shanxi Province, China
- Coordinates: 35.590983, 111.376042 (exact)
- Status: Operating
- Gross capacity: 600 MW (Units 1 & 2: 300 MW)
- Type: Subcritical
- Projected in service: 2014
- Coal type: Bituminous
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "火电巨头纷纷缓建项目困局难解", 新浪财经, 2013-02-13
- ↑ "漳泽电力侯马热电联产项目投产发电," 中国证券报, 2014-11-18
- ↑ "同煤集团电力发展跑赢目标", 人民网山西频道, 2014-02-25
- ↑ "召开2×300MW热电联产工程1#机组启动验收委员会会议", 山西漳泽电力股份有限公司, 2014-8-28
- ↑ "Chinese nuclear giant officially launched", World Nuclear Association (16 July 2015). Retrieved on 4 May 2015.