China Resources Caofeidian power station (华润电力唐山曹妃甸公司一期) is a 1,600-megawatt (MW) coal-fired power plant in Hebei Province, China.
An additional 1,000 MW is under development.
Contents
Location
The map below shows the location of the plant, in Caofeidian District, Tangshan Prefecture, Hebei Province.
Background on Plant
The two existing coal-fired units of China Resources Caofeidian power station, totaling 600 MW, were brought online in 2009. The plant is owned by China Resources, and was constructed by Tangshan City Construction Investment Co.[1][2] It is a heat and electricity co-generation power plant. The power plant was complained by local residents in 2015 for its air pollution caused by its uncovered coal storage.[3]
Expansion
China Resources is currently building two additional coal-fired units at this plant, with a total planned capacity of 2,000 MW. The new units were scheduled to be completed in 2015, [4] but as of 2017 are still under construction.[5]
Unit 3 was commissioned in May 2019.[6]
Plant Details for Existing Units 1 & 2
- Sponsor: China Resources (90%), Tangshan Construction Investment (10%)
- Location: Caofeidian District, Tangshan Prefecture, Hebei Province, China
- Coordinates: 38.9960653, 118.4875488 (exact)
- Status: Operating
- Gross capacity: 600 MW (Units 1 & 2: 300 MW)
- Type: Subcritical
- Start year: 2009
- Coal type:
- Coal source:
- Source of financing:
Project Details for Units 3 & 4 Expansion
- Sponsor: China Resources (90%), Tangshan Construction Investment (10%)
- Location: Caofeidian District, Tangshan Prefecture, Hebei Province, China
- Coordinates: 38.9960653, 118.4875488 (exact)
- Status: Operating (Unit 3), Construction (Unit 4)
- Gross capacity: 2,000 MW (Units 3 & 4: 1,000 MW)
- Type: Ultra-Supercritical
- Start year: 2019
- Coal type: Bituminous
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "曹妃甸积极谋划与北京共同推进曹妃甸产业园建设“, 曹妃甸信息港, 2014-07-23
- ↑ "曹妃甸开发建设的情况介绍", 唐山市曹妃甸区商务之窗, 2013-05-16
- ↑ "华润曹妃甸电厂被举报任意堆放粉煤 污染环境," 手机看新闻, 2015-02-04
- ↑ "The EIA Report of the Second phase of Caofeidian power station"天津市环境保护科学研究院, 2013-5
- ↑ "华润电力曹妃甸电厂二期建设犹酣"中国经济网, 2017-9-07
- ↑ "华润曹妃甸电厂3号机组节能减排工程投产发电," 中国电建核电公司, 2019/5/8