Collinsville (Shine Energy) power station

From SourceWatch
Jump to navigation Jump to search

Collinsville (Shine Energy) power station is a proposed 1000 MW coal plant to be located at or near the now closed Collinsville power station. The plant has been proposed by Shine Energy Australia, a company with no coal power plant experience.

Background

According to Shine Energy, a concept study for its proposed coal plant was undertaken by the enginnering company WSP and a business case for the project completed at the end of 2018.[1]

On March 26, 2019 Prime Minister Scott Morrison announced that 12 projects had been short-listed for possible funding from the Underwriting New Generation Investments program including a coal plant upgrade proposed by Delta Electricity, a company co-owned by Trevor St Baker.[2]

While the Collinville plant was not on the shortlist, Morrison announced that the "government will conduct detailed evaluation and feasibility of projects in North and Central Queensland through the Underwriting New Generation Investments program. These projects include but are not limited to a new HELE coal project in Collinsville, upgrades of existing generators as well as gas and hydro projects."[2]

The Australian reported that "the proposed project has received the initial backing of resources giant Glencore which said it would provide Shine Energy with 'project management and governance expertise during the feasibility phase of the project'".[1]

In June 2019 Shine Energy CEO Ashley Dodd said that the company planned to raise A$2 billion and complete construction of the plant by October 2020.[3] In October 2019 Senator Matthew Canavan, Minister for Resources and Northern Australia, expressed support for a feasibility study for the project.[4]

Location

The map below shows the location of the now closed Collinsville power station near Collinsville, Queensland. The location of the proposed new plant is likely to be at the same site or nearby.

Loading map...

Plant Details

  • Sponsor: Shine Energy
  • Parent company: Shine Energy
  • Location: Mannering Park, New South Wales, Australia
  • Coordinates: -20.5450506, 147.8045568 (approximate)
  • Status: Announced
  • Gross capacity: 1000 MW
  • Type:
  • In service: 2020
  • Coal type: Black
  • Coal source: Queensland
  • Source of financing:

Contact details

Brisbane Technology Park,
Clunies Ross Court,
Eight Mile Plains QLD 4113
Phone: 07 3188 9319
Website: https://www.shineenergy.com.au/

Articles and Resources

Related SourceWatch Articles

References

  1. 1.0 1.1 "Indigenous generator seeks carbon promise", The Australian, March 27, 2019.
  2. 2.0 2.1 Prime Minister Scott Morrison, "Delivering affordable and reliable power", Media Release, March 26, 2019.
  3. AUSTRALIA: $2BN TARGET FOR COMPANY BEHIND BOLD INDIGENOUS POWER PROJECT, IEA, Jun. 11, 2019
  4. Canavan 'desperate' for coal-fired power in pledge to back projects, Sydney Morning Herald, Oct. 30, 2019