Project Summary
Hyperion is in the planning stage for a new $10 billion, 400,000 bpd oil refinery to process synthetic crude from the tar sands and an associated "integrated gasification combined cycle" (IGCC) power plant. This project is sometimes called the "Gorilla Project," due to its size.[1]
Permitting Status
PSD permit application submitted Dec. 20, 2007. South Dakota Department of Environment & Natural Resources (SDDENR) determined application to be complete on Feb. 20, 2008. Comments currently being accepted on the application. The project is also an item in a Union County Referendum to be held June 3, 2008.[1]
External links
Relevant Documents
- [1] PSD permit application and associated documents