Fuzhou Kemen power station (华电可门电厂) is a 2,400-megawatt (MW) coal-fired power plant in Fujian Province, China.
Contents
Location
The map below shows the location of the plant, at Lianjiang County, Fuzhou Prefecture.
Background on Plant
The four existing coal-fired units of Fuzhou Kemen power station, totaling 2,400 MW, were brought online between 2006 and 2008. The plant is owned by China Huadian.[1]
Description of Expansion
Huadian is currently planning to build two additional coal-fired units at this plant, with a total planned capacity of 2,000 MW. The new units were scheduled to be completed in 2016.[2][3][1]
The proposed units were permitted in 2015. They are planned for commissioning in 2018.[4]
2017: Expansion postponed by government
In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[5]
Fuzhou Kemen power station Units 5-6 are among the postponed coal-burning units,[5] and also appeared on an updated list of postponements released in September 2017.[6]
For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.
Plant Details for Existing Phases I & II
- Sponsor: Huadian Fuxin Energy Corp Ltd
- Parent company: Huadian
- Location: Yanqi Village, Kengyuan Town, Lianjiang County, Fuzhou Prefecture, Fujian Province, China
- Coordinates: 26.3733242, 119.7622253 (exact)
- Status: Operating
- Gross capacity: 2,400 MW (Units 1-4: 600 MW)
- Type: Supercritical
- In service: 2006 (Units 1 & 2); 2008 (Units 3 & 4)
- Coal type:
- Coal source:
- Source of financing:
Project Details for Phase III Expansion
- Sponsor: Huadian Fuxin Energy Corp Ltd
- Parent company: Huadian
- Location: Luoyuan Bay, Lianjiang County, Fuzhou Prefecture, Fujian Province, China
- Coordinates: 26.3733242, 119.7622253 (exact)
- Status: Shelved (postponed by government policy in July 2017)
- Gross capacity: 2,000 MW (Units 5 & 6: 1,000 MW)
- Type: Ultra-Supercritical
- Projected in service:
- Coal type: Bituminous
- Coal source:
- Source of financing: 4.15 billion yuan[3]
Articles and resources
References
- ↑ 1.0 1.1 “福建华电可门电厂三期工程环境影响评价信息公示(第二次,” 福建日报, 2014-04-17
- ↑ Ailun Yang and Yiyun Cui, "Global Coal Risk Assessment: Data Analysis and Market Research," World Resources Institute working paper, November 2012
- ↑ 3.0 3.1 "福建可门电厂二期工程已获核准," accessed June 2013
- ↑ "华电可门三期2×1000MW清洁高效火电项目获核准," 来源:北极星电力网, 2015/11/19
- ↑ 5.0 5.1 "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12