Huadian Turpan power station
This article is part of the CoalSwarm coverage of China and coal | |
Sub-articles: | |
The Huadian Turpan power station (华电吐鲁番发电公司一期) is a retired 270-megawatt (MW) coal-fired power station in Xinjiang province, China.
A 1,320-megawatt (MW) coal-fired expansion was proposed, also known as Huadian Toksun power station (华电吐鲁番发电公司二期), but the project has been abandoned. The proposal is different from the Huadian Turpan Cogen power station.
Contents
Location
The undated satellite photo below shows the proposed location for the plant in Toksun county.
Background on Plant
The plant's two units are 135 MW each and began operating in 2006. The plant is in Turpan prefecture and majority-owned by China Huadian.[1]
The two units were retired in October 2019.[2]
Expansion
In 2014 China Huadian's Xinjiang Huadian Power Generation Company signed a framework agreement with the Turpan Prefecture Government to build an additional two units of 350 MW each at the plant.[3] The feasibility study has been completed.[4]
2016: Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
Due to new restrictions announced during 2016 by the National Energy Administration and the National Development and Reform Commission, further capacity expansions at this location appear to be on hold or cancelled. For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
Project Details of expansion
- Sponsor: Huadian Xinjiang Power Co Ltd
- Parent company: China Huadian (98%), Tokson Asset Investment Management (2%)
- Location: Toksun county, Turpan prefecture, Xinjiang province, China
- Coordinates: 42.730583, 88.617 (exact)
- Status: Cancelled
- Capacity: 1,320 MW (Units 3-4: 660 MW)
- Projected in service:
- Type: Supercritical
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "吐鲁番地区与华电新疆发电公司签署合作框架协议," 吐鲁番日报, 2014-07-02
- ↑ "关于新疆维吾尔自治区2019年度煤电行业淘汰落后产能任务完成情况的公告," 电力处, 2019-11-25
- ↑ "吐鲁番地区与华电新疆发电公司签署合作框架协议," 吐鲁番日报, 2014-07-02
- ↑ "华电新疆托克逊发电厂一期(2×660MW)工程通过可研审查," CEDC, date unknown