The Huaneng Xining power station (华能西宁热电厂一期项目) is a 700-megawatt (MW) coal-fired power station in Qinghai province, China.
Contents
Location
The photo below shows the power station in Xibao Town.
Loading map...
Background on Plant
The proposed power station by China Huaneng and Qinghai SASAC would consist of two units of 350 MW each. The power station began construction in 2014.[1] It is planned for operation in 2015 to 2016.[2]
Unit 1 was commissioned in 2015,[3] and unit 2 in 2016.[4]
Project Details
- Sponsor: China Huaneng (80%), Qinghai SASAC (20%)
- Location: Xibao Town, Baozi Village, Huangzhong county, Xining Prefecture, Qinghai Province, China
- Coordinates: 36.628797, 101.628752 (exact)
- Status: Operating
- Gross capacity: 700 MW (Units 1 and 2: 350 MW)
- Projected in service: 2015 (Unit 1), 2016 (Unit 2)
- Type: Supercritical
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "华能西宁热电一期2×350MW热电厂项目 变更环境影响评价第一次公示," 青海日报, 2014-5-22
- ↑ "华能西宁热电(2×350MW)机组全厂维护前期准备工作全面展开," 2015-8-6
- ↑ "015年度拟在建300MW火力发电工程项目汇总," 中国电力化工网点击, 2015-11-17