Jiaozuo Bo'ai power station
This article is part of the Coal Issues portal on SourceWatch, a project of Global Energy Monitor and the Center for Media and Democracy. See here for help on adding material to CoalSwarm. |
This article is part of the CoalSwarm coverage of China and coal | |
Sub-articles: | |
Jiaozuo Bo'ai power station (华润焦作龙源电厂上大压小新建项目) is a 1,320-megawatt (MW) coal-fired power plant in Henan Province, China.
Contents
Location
The undated satellite photo below shows the power station in Bo'ai County.
Background on Plant
The two existing coal-fired units of Jiaozuo Boai power station, totaling 270 MW (2 x 135 MW), were brought online in 2005. The plant is owned by China Resources.[1] It is also referred to as the Wanfang-2 power station.
The units were retired in 2015, after the new units 3-4 came online.[2]
Expansion
China Resources planned two additional coal-fired units at this plant, units 3 and 4, with a total capacity of 1,320 MW. Construction of the plants began in 2013.[3][4] Unit 3 was completed in 2014,[5] and unit 4 in 2015.[6]
Plant Details for Existing Units 1 & 2
- Sponsor: China Resources Power Holdings
- Parent company: China Resources
- Location: Yanzhuang Village, Baishan Town, Bo'ai County, Jiaozuo Prefecture, Henan Province, China
- Coordinates: 35.221015, 113.102206 (exact)
- Status: Retired (2015)
- Gross capacity: 270 MW (Units 1 & 2: 135 MW)
- Type: Subcritical
- In service: 2004
- Coal type:
- Coal source:
- Source of financing:
Project Details for Units 3 & 4 Expansion
- Sponsor: China Resources
- Location: Yanzhuang Village, Baishan Town, Bo'ai County, Jiaozuo Prefecture, Henan Province, China
- Coordinates: 35.221015, 113.102206 (exact)
- Status: Operating
- Gross capacity: 1,320 MW (Units 3 & 4: 660 MW)
- Type: Ultra-supercritical
- In service: 2014 (Unit 3), 2015 (Unit 4)
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "Annual Report," China Resources Power, 2005
- ↑ "关于撤除焦作华润热电有限公司环境监管记录的说明," IPE, 2015-10-21
- ↑ "华润焦作2×660MW机组工程2号机组正式开工", 中国电力网, 2013-07-18
- ↑ "50亿投资能源建设逆市布局 龙源电厂雄踞城西蓄势展翼", 焦作网, 2013-10-9
- ↑ "华润电力焦作龙源电厂2×660兆瓦超超临界火电机组工程投运," 焦作日报, 2015/1/7
- ↑ "华润焦作龙源电厂2号机组通过168小时试运行," Power Construction Corp. of China, 2015-06-03