Jingneng Energy Jining power station (京能内蒙古京宁热电公司) is a 700-megawatt (MW) coal-fired power plant in Inner Mongolia Autonomous Region, China.
Contents
Location
The undated satellite photo below shows the plant in Jining city.
Loading map...
Background on Project
Beijing Energy Group is constructing a 2 x 350 MW supercritical coal plant in the city of Jining. It started construction before it received environmental approval, therefore, the provincial environmental authority ordered the halt of the construction.[1] It was permitted in 2015,[2][3] and completed in 2016.[4]
Project Details
- Sponsor: Beijing Energy Group
- Location: Jining city, Ulanqab (Wulanchabu) Prefecture, Inner Mongolia Autonomous Region, China
- Coordinates: 41.053294, 113.153289 (exact)
- Status: Operating
- Gross capacity: 700 MW (Units 1-2: 350 MW)
- Type: Supercritical
- Start date: 2016
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "内蒙古自治区环境保护厅责令改正违法行为决定书"内蒙古环保厅, 2015-05-20
- ↑ "京能集宁热电联产机组工程正式获得核准," Baotou Teng Bang Spray, 2015年7月29日
- ↑ "京能集宁热电工程2号机组汽轮机扣盖一次成功," 集宁项目部, 2015-9-1