Kaita power station
This article is part of the Coal Issues portal on SourceWatch, a project of Global Energy Monitor and the Center for Media and Democracy. See here for help on adding material to CoalSwarm. |
This article is part of the CoalSwarm coverage of Japan and coal. |
Sub-articles: |
The Kaita power station is a proposed 112-megawatt (MW) co-fired coal and biomass power station in Hiroshima prefecture, Japan.
Contents
Location
The map below shows the town of Kaita, the proposed location for the power station
Background
The co-fired coal and biomass power station is proposed by Chugoku Power Company and Hiroshima Gas (HG) at the site of HG's old Kaita factory. The companies plan to submit the EIA in FY 2015-6, begin construction in 2018, and complete the power station by 2021.[1][2]
The EIA process was complete as of July 2018, according to the Kiko Network.[3]
According to the Kiko Network, construction began in December 2018.[4][5]
Project Details for Misumi power station Expansion
- Sponsor: Kaita Biomass Power Co.
- Parent Company: Chugoku Electric Power 50%; Hiroshima Gas 50%
- Location: Kaita town, Hiroshima prefecture, Japan
- Coordinates: 34.366667, 132.533333 (approximate)
- Status: Construction
- Gross Capacity: 112 MW
- Type: Subcritical
- Projected in service: 2021
- Coal Type: biomass and coal
- Coal Source:
- Source of financing:
Articles and resources
References
- ↑ 海田地区バイオマス混焼発電所の事業可能性検討における 環境影響評価手続きの着手について," Hiroshima Gas, 27-3-2014
- ↑ Kaita biomass blend firing power station, Kiko Network, accessed Dec. 2017
- ↑ Kaita biomass blend firing power station, Kiko Network, July 2018
- ↑ バイオマス混焼発電所着工へ、中国電と広島ガス 広島県海田町, Nikkei, Dec. 10, 2018
- ↑ Kaita power station (Biomass), Kiko Network, accessed February 2019