Ketu North power station
Part of the Global Gas Plant Tracker, a Global Energy Monitor and Center for Media and Democracy project. |
Ketu North power station was a proposed 2,000-megawatt (MW) gas-fired power plant in Volta Region, Ghana.[1]
As of December 2019, the project has not progressed in more than four years and appears to be cancelled.
Location
The map below shows the approximate location of the proposed power station in Dzodze - Ketu North District, Volta Region, Ghana.
Background
The MacBaron Group announced plans to build the Ketu North power plant in January 2013. The Ketu power plant project is meant to be a base load provider for the West Africa Power Pool (WAPP).[1] The project will use liquefied natural gas brought in by train until piped natural gas becomes available.[2] In April 2013, local communities announced that they had set aside land for the project.[3]
The project has been delayed due to government regulatory issues.[4]
Project Details
- Sponsor: MacBaron Group
- Parent company: MacBaron Group
- Location: Dzodze - Ketu North District, Volta Region, Ghana
- Coordinates: 6.2420, 0.9964 (approximate)
- Gross capacity (cancelled): 2,000 MW
- Combined-cycle units 1-5: 400 MW each (no start-up date)
Articles and Resources
References
- ↑ 1.0 1.1 Plans for 2,000 MW CCGT facility in Ghana, ESI Africa, Jan 17, 2013
- ↑ Private firm to provide Ghana 2000 megawatts of power, Skyscraper City, Mar 2012
- ↑ [1], GhanaWeb, Apr 17, 2013
- ↑ MBG – Ketu Power Plant 2000 MW – Volta - Project Profile, Market Research, Jun 2017