Linyou Waste Coal power station
{{#badges:CoalSwarm|Navbar-Chinacoal}} Linyou Waste Coal power station (陕西省投资集团麟北发电公司) is a 700-megawatt (MW) coal-fired power station in Shaanxi province, China.
Contents
Location
The undated satellite photo below shows the location of the plant in Liangting Town, Linyou County.
Background on Plant
Shaanxi Provincial Investment Group is seeking approval for a 2 x 350 MW waste coal plant in Linyou County.[1] A feasibility study was completed in November 2015.[2]
The project received environmental clearance from the Shaanxi Provincial DRC in June 2016.[3]
Construction began in 2016.[4]
2017: Plant postponed by government
In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[5]
Linyou Waste Coal power station Units 1-2 are among the halted coal-burning units,[5] and also appeared on an updated list of halted projects released in September 2017.[6]
For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.
Construction ongoing
Satellite photos from Planet from July 2017 to May 2018 suggest construction is not only ongoing but rapid, with the coal plant near completion.
2019: Plant commissioned
Unit 1 was commissioned in January 2019.[7] Unit 2 was commissioned in April 2019.[8]
Project Details
- Sponsor: Shaanxi Qinlong Electric Power Co
- Parent company: Shaanxi Provincial Investment Group
- Location: Shuangting Town, Linyou County, Baoji Prefecture, Shaanxi Province, China
- Coordinates: 34.910101, 107.554315 (exact)
- Status: Operating
- Gross capacity: 700 MW (Units 1&2: 350 MW)
- Start year: 2019
- Type: Supercritical
- Coal type: Waste coal
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "我县第一个煤产业化项目落地建设," 县发改局, 2015年8月11日
- ↑ "陕西能源集团麟游2×350MW低热值煤发电项目工程顺利通过评审," 中国火力发电网, 2015-11-26
- ↑ "秦龙电力麟游低热值煤发电工程项目获得省发改委核准"秦龙电力新闻,2016/7/29
- ↑ "陕西能源集团麟游低热值煤发电工程主厂房第一罐混凝土浇筑暨开工仪式顺利举行," 陕西能源集团, 2016-8-31
- ↑ 5.0 5.1 "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
- ↑ "陕能麟游1号机组完成168小时满负荷试运行-国际电力网," power.in-en, 2019-01-21
- ↑ "陕能麟北发电厂2×350MW工程2号机组168小时试运圆满完成," 西北电建三公司, 2019/5/6