{{#badges:CoalSwarm|Navbar-Chinacoal}}Muguajie Gangue power station (中煤平朔第一煤矸石发电有限公司), also known as Pingshuo Waste Coal Power Plant, is a proposed 1,320-megawatt (MW) waste coal-fired power plant in Shanxi Province, China.[1][2]
Contents
Location
The undated satellite photo below shows the construction site in Pinglu District.
Background on Project
ChinaCoal and partners are currently planning to build a waste coal-fired power plant with a total planned capacity of 1,200 MW in Shanxi Province.[3][4] The power station is under construction.[5]
Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
In January 2017 China's National Energy Administration suspended over 100 planned and under-construction coal power projects with a total capacity of over 100GW in 13 provinces, including Muguajie Gangue power station. It is unclear when or if the projects will be revived.[6] For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
2017: Plant postponed by government
In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[7]
Muguajie Gangue power station Units 1-2 are among the postponed coal-burning units,[7] and also appeared on an updated list of postponements released in September 2017.[8]
For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.
Construction resumed
Construction resumed on unit 1 following the suspension, but in May 2018 unit 1 was ordered to obtain a permit to continue construction.[9]
Project Details
- Sponsor: ChinaCoal (51%), China Datang (34%), Dongfang Electric Corporation (15%)
- Location: Muguajie village, Pinglu District, Shuozhou Prefecture, Shanxi Province, China
- Coordinates: 39.5468703, 112.3119811 (exact)
- Status: Shelved
- Gross capacity: 1,320 MW (2 x 660 MW)
- Type: Supercritical
- Projected in service:
- Coal type: Waste coal
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "山西中煤平朔低热值煤发电新建项目环境影响评价信息公示",平鲁政府网,2014-04-30
- ↑ "低热值煤发电的山西攻略", 中国经济网, 2014-05-12
- ↑ "海委关于山西中煤平朔低热值煤发电新建项目水资源论证报告的批复(海许可(2013)22号)", 水信息网, 2013-06-05
- ↑ "平朔 2×660MW CFB低热值煤电厂项目获得“路条”", 朔州市新闻中心, 2013-03-26
- ↑ "山西省政府督查朔州低热值煤发电项目进展情况," ce5e.cn, May 8, 2015
- ↑ "能源局下发13省市新建火电机组停建清单(附文件)," Polaris, Jan 16, 2017
- ↑ 7.0 7.1 "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
- ↑ "安徽电建一公司中煤平朔项目1号机组主变就位完成," China Power, 2018-05-03