{{#badges:CoalSwarm|Navbar-Japanandcoal}} The Noshiro power station is a 1,200 megawatt (MW) coal-fired power station in Noshiro, Japan.
An additional 600 MW is under construction.
Contents
Location
The undated satellite photo below shows the plant.
Background on Plant
The existing station consists of two 600 MW units and is owned by Tohoku Power Company. They began operating in 1993-1994.[1]
Description of Expansion
A proposed 600 MW Unit 3 would use liquefied natural gas and coal, originally scheduled for 2028.[2]
A 2014 Tepco document states bids for construction will begin in 2014 and construction in 2016, with a planned completion date of 2020.[3]
Construction of a coal-fired 600-MW unit began in February 2016.[4] It is scheduled for completion in March 2020.[4] According to the Kiko Network trial operations began in August 2019.[5]
Project Details for Noshiro power station Expansion
- Sponsor: Tohoku Electric Power Company (Tepco)
- Parent Company: Tohoku Electric Power Company (Tepco)
- Location: Noshiro, Akita, Japan
- Coordinates: 40.1912, 139.9911 (exact)
- Status: Construction
- Gross Capacity: 600 MW
- Type: Ultra-supercritical
- Projected in service: 2020
- Coal Type: Bituminous
- Coal Source:
- Source of financing:
Articles and resources
References
- ↑ Federation of Electric Power Companies of Japan, "Principal Thermal Power Plants (1,000MW or greater)", Federation of Electric Power Companies of Japan, accessed August 2009.
- ↑ "Japan hot on coal as 5,400 MW of new projects are in the pipeline," Power Insider, October 16, 2013.
- ↑ Description of new unit (Japanese), Tepco, accessed July 2014.
- ↑ 4.0 4.1 "Noshiro No.3 / Tohoku Electric Power / Noshiro city, Akita pref.," Kiko Network, accessed June 2016
- ↑ Noshiro power station Unit 3, Kiko Network, accessed November 2019