{{#badges:CoalSwarm|Navbar-Chinacoal}}Ordos Shuangxin power station (双欣能源化工集团发电项目) is a 1,060-megawatt (MW) coal-fired power plant in Inner Mongolia Autonomous Region, China.
Contents
Location
The map below shows the plant in Otog Front Banner.
Background on Plant
The 400 MW power station (2 x 200 MW) has been in operation since 2008. It is owned by Ordos Share Holding Group.[1][2] An additional 2 x 330MW was commissioned in 2010.[2][3][4][5]
Proposed expansion
Ordos Share Holding Group has proposed expanding the power station by two 600 MW units.
2016: Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
Due to new restrictions announced during 2016 by the National Energy Administration and the National Development and Reform Commission, further capacity expansions at this location appear to be on hold or cancelled. For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
The restrictions likely cancel plans by Ordos Share Holding Group to expand the power station by two 600 MW units.
Project Details
- Sponsor: Ordos Share Holding Group
- Location: Mengxi Town, Otog Banner, Ordos (E'erduosi) Prefecture, Inner Mongolia Autonomous Region, China
- Coordinates: 39.385235, 106.965664 (exact)
- Status: Operating (Units 1-4); Cancelled (Units 5-6)
- Gross capacity: 1,060 MW (Units 1-2: 200 MW, Units 3-4: 330 MW); 1,200 MW (Units 5&6: 600 MW)
- Type: Supercritical (Units 3-4)
- In service: 2008 (Units 1-2), 2010 (Units 3-4)
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "鄂尔多斯电力(集团)有限责任公司企业简介," Erdos website, accessed Sep 2015
- ↑ 2.0 2.1 "鄂尔多斯双欣电力有限公司招聘启事," Inner Mongolia Normal University, 2015-06-12
- ↑ "内蒙古双欣能源化工有限公司2×350MW低热值煤 发电工程环境影响评价公众参与第二次公示," 蒙西工业园区管委会 作者, 2015/7/31
- ↑ "棋盘井自备电厂二期扩建工程获核准," 2015-09-01