Parit Baru power station
{{#badges:CoalSwarm|Navbar-Indonesiacoal}}Parit Baru power station is a 210-megawatt (MW) coal-fired power station under development in West Kalimantan Province, Indonesia.
Contents
Location
The map below shows the plant, in Jungkat Village, Siantan District, Pontianak Regency, West Kalimantan Province.[1] Planet satellite photos show construction progress from April 2016 to April 2018.
Background
Units 1 & 2
Work on the Parit Baru project began in 2010 and completion was initially targeted for 2012.[2] It was the first coal plant EPC (engineering, procurement, and construction) contract undertaken by a joint venture comprising Gazhouba Group in Indonesia (a subsidiary of China Energy Engineering Corporation) and PT Praba Indopersada (a subsidiary of general contractor firm Praba Group of Indonesia).[3] In May 2011 it was estimated that the project would cost US$172 million. The project is 85% financed by the Export-Import Bank of China.[4] The joint venture between the two companies was formalized in a memorandum of understanding at the conclusion of a three day visit to Indonesia by Chinese Premier Wen Jiabao. On the trip Jiabao pledged $19 billion in investment and loans to a range of projects in Indonesia.[3][5]
In March 2013, 78 Chinese-national workers at the Parit Baru construction site were threatened with deportation for lacking proper work authorization.[6] Hundreds of Chinese workers were repatriated in 2013.[2] According to the 2015-2024 PT PLN supply plant, Parit Baru 1 and 2 will be completed in 2016.[7] However, in November 2016 it was reported that construction on the units had been delayed.[8]
In September 2013, construction resumed on the project.[9] The project faces the South China sea in the west and is adjacent to the Pontianak-Singkawang provincial highway. It occupies 40 hectares. According to the contract, construction will be completed in 33 months.[9] In November 2016, the Operations and Construction Manager of PT PLN West Kalimantan Development Master Unit, I Wayan Semudiarsa, said that the Parit Baru project was experiencing financial difficulties and progress was slow.[10]
In March 2017, President Joko Widodo stated that after seven years the legal problems that had delayed the plant were resolved and the plant was moving toward completion.[11]
In June 2018 Unit 1 was commissioned.[12]
The long-range plan for 2019-2028 lists 100 MW from Parit Baru FTP1 being commissioned in 2019, and 50 MW from Parit Baru FTP2 in 2019.[13] Unit 2 was commissioned in August 2019.[14]
Units 3 & 4
The project has since been expanded by two additional 50-MW coal-fired units, listed as scheduled to be completed in 2017-18.[5] As of April 2016, these units had not yet begun construction, as shown by Google Earth archival imagery. According to the 2015-2024 PT PLN supply plant, Parit Baru Units 3 and 4 will be completed in 2017 and 2018 respectively.[7]
Project Details
- Sponsor: Gezhouba Group and PT Praba Indopersada
- Parent: China Energy Engineering Corporation and Praba Group
- Location: Jungkat Village, Siantan District, Pontianak Regency, West Kalimantan Province
- Coordinates: 0.05798, 109.20362 (exact)
- Status: Unit 1: Operating; Unit 2: Operating; Units 3-4: Pre-permit development
- Gross Capacity: 200 MW (Units 1 & 2: 50 MW; Units 3 & 4: 55 MW)
- Type: Subcritical
- Projected in service: Unit 1: 2018; Unit 2: 2019; Units 3-4: 2019
- Coal Type:
- Coal Source:
- Source of financing: Export-Import Bank of China[15]
Articles and resources
References
- ↑ PLTU Parit Baru, Jungkat, Pnk., Wikimapia, accessed Mar. 2015.
- ↑ 2.0 2.1 "Menyoal Pembangunan PLTU di Kalbar," Pontianakpost.co.id, 2 June 2016
- ↑ 3.0 3.1 Linda Yulisman, "Chinese firm to build coal-fired power plant in W. Kalimantan", Jakarta Post, May 03 2011.
- ↑ PLTU Dengan Daya 2x50 MW Segera Diabangun, West Kalimantan Provincial Government press release, 9 Sept. 2013.
- ↑ 5.0 5.1 Rencana Strategis (Strategic Plan) KESDM 2015-19, Indonesia Ministry of Energy & Natural Resources, 24 Feb. 2015.
- ↑ 78 Pekerja PLTU Asal Cina Terancam Deportasi, Republika, 20 Mar. 2013.
- ↑ 7.0 7.1 "Executive Summary: Electricity Supply Business Plan, PT PLN (Persero) 2015-2014,"
- ↑ "PLN unveils details of 34 troubled power plants under SBY govt being probed by KPK," Rambu Energy, November 24, 2016
- ↑ 9.0 9.1 "Parit Baru Coal Fired Power Plant Construction Commenced," China Gezhouba (Group) Corporation press release, September 7, 2013
- ↑ "PLN: Dua Proyek Pembangkit Di Kalbar Masih Terkendala," AntaraKalbar.com, 14 November 2016
- ↑ "Jokowi Singgung PLTU Parit Baru Mangkrak," IndonesiaOversight, 19 March 2017
- ↑ PLN Operasikan PLTU Baru 50 MW di Kalimantan Barat, Industri, Jun. 6, 2018
- ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2019-2028, PT PLN Persero, V-51
- ↑ PLTU Parit Baru Site Bengkayang kapasitas 100 MW sudah beropersi penuh, Kalbar, Aug. 22, 2019
- ↑ PLTU Dengan Daya 2x50 MW Segera Diabangun, West Kalimantan Provincial Government press release, 9 Sept. 2013