Point Aconi Generating Station

From SourceWatch
Jump to navigation Jump to search
Coalswarm badge.gif

This article is part of the Coal Issues portal on SourceWatch, a project of Global Energy Monitor and the Center for Media and Democracy. See here for help on adding material to CoalSwarm.

Point Aconi Generating Station is a 165-megawatt (MW) coal-fired and petcoke-fired power station in Point Aconi, Nova Scotia, Canada.[1]

As of 2005 the plant was 80% fired by petcoke and 20% fired by coal.[2]

Location

The map below shows the plant in Point Aconi, Nova Scotia, Canada.

Loading map...

Background

The Seaboard Generating Station opened in Glace Bay, Nova Scotia in 1931 by Dominion Steel and Coal Corporation and was the sole supplier of electricity for the Industrial Cape Breton region until its purchase by Nova Scotia Power in 1966 as part of DOSCO's ongoing asset liquidation. Nova Scotia Power opened the province's largest generating station, the Lingan Generating Station, at the height of the 1979 energy crisis to take advantage of relatively cheap Cape Breton coal being produced by the Cape Breton Development Corporation (DEVCO).

The idea of replacing the aging Seaboard Generating Station was discussed during the 1980s and was an important promise by the incumbent Progressive Conservative Association of Nova Scotia led by Premier John Buchanan during the Nova Scotia general election of 1988. After Buchanan's government was returned to power, Nova Scotia Power issued a call for proposals in October 1988 to construct a 150 megawatt CFB (Circulating Fluidized Bed) coal-fired electrical generating station in Point Aconi.

Significant controversy dogged Buchanan's election promise to build a new generating station as the Nova Scotia Utility and Review Board had authority to decide on all applications by Nova Scotia Power to construct new generating stations as well as associated rate increases. The PUB began to conduct hearings into the project in spring 1989 and stated that an economic analysis of Buchanan's election promise (the $500 million Point Aconi Generating Station) was not required as the province's generating needs were met by current sources. Coincidentally, Nova Scotia Power had also promised to purchase 30 megawatts annually from small independent power producers in the province beginning in 1990, however this agreement was abolished after the Small Private Power Association of Nova Scotia intervened at the PUB hearings to block the proposed Point Aconi Generating Station. On April 27, 1989, Buchanan introduced a controversial amendment to the Public Utilities Act which would remove the requirement for Nova Scotia Power to submit proposals for new generating station to the PUB. PUB hearings into the Point Aconi project were cancelled after the amendment to the Public Utilities Act receiving Royal Assent in early June 1989.[3]

In early January 1990, Nova Scotia Power announced that the Japanese industrial conglomerate Mitsui had won the RFP that had been issued in fall 1988 and a contract was signed on behalf of the Government of Nova Scotia. The proposal detailed a turnkey project designed by Mitsui with the CFB steam boiler supplied by Pyro-Power through Kamtech Services (a subsidiary of The Lauren Corporation of Abilene, Texas), project management and engineering by Chicago-based Sargent & Lundy LLC, and construction of the plant itself by Jones Power Corporation. Two weeks later, the provincial government announced that its Environmental Control Council would conduct a one-day hearing into the project on January 18, 1990 in place of the PUB hearings conducted the previous spring which were aborted as a result of the amendment to the Public Utilities Act. This hearing received submissions from citizens and organizations that were strongly opposed to the Point Aconi Generating Station, pointing out the environmental impact, that its generating capacity wasn't required, and that it was a political mega-project that would add to the financial debt of the publicly owned Nova Scotia Power Corporation. Other submissions from citizens and organizations were supportive of the project, which they claimed would create an estimated 500 construction and operating jobs, as well as theoretically guarantee work in Cape Breton's coal mines; the United Mine Workers of America Local 26 had lobbied hard for the power plant. Richie Mann, the environment critic for the official opposition Nova Scotia Liberal Party asked at the one-day hearing "Can you give us some evidence that this process is not an exercise in public relations, a sham?"[4]

On Friday, March 9, 1990 the provincial government announced its approval of the estimated $436 million project, even though it had already signed a contract with Mitsui two months earlier. Nova Scotia's Environment Minister John Leefe defended the projected 1.5 million tonnes of carbon dioxide emissions, stating "[The project will be] absolutely inconsequential in terms of global carbon dioxide production."[5]

Nova Scotia Power pointed out the environmental benefits of the Point Aconi project, stating that the use of CFB technology whereby limestone would be used to filter out sulphur dioxide and nitrogen oxide which were major contributors to acid rain. Minister Leefe stated that Nova Scotia Power intended to reduce SO2 emissions from its generating stations to 100,000 tonnes a year by 2010 from the 1990 level of 160,000 tonnes. Minister Leefe also noted that while the use of CFB technology would reduce acid rain, it would also result in a comparatively massive increase in carbon dioxide emissions which was a greenhouse gas; Leefe told reporters that Nova Scotia's coal-fired plants contributed 32 per cent of the 18 million tonnes per year of CO2 emitted by the province (as of 1990). The projected increase in Nova Scotia's Co2 emissions as a result of the Point Aconi Generating Station (an estimated additional 1.5 million tonnes per year) went against a recent (1990) decision by federal and provincial energy ministers to reduce emissions of the gas by at least 20 per cent by 2005.[6]

The debate over construction of the Point Aconi Generating Station took place in the shadow of a much larger global debate over acid rain and its contributing factors, such as fossil fueled generating stations. The acid rain controversy resulted in the Canada-United States Air Quality Agreement which was signed by both countries on March 13, 1991 and stipulated that both countries would agree to reduce emissions of sulphur dioxide (SO2) and nitrogen oxide (NOx).[7]

On September 20, 1990, federal Minister of Fisheries and Oceans Bernard Valcourt rejected a full environmental review of the project, arguing that any problems to the environment would be relatively minor. Valcourt justified this decision by referring to a scientific report on the project conducted by the Department of Fisheries and Oceans which stated that use of CFB technology could be mitigated. It noted, however, the widespread concern of local residents over the effect of the generating station's draw on ground water supplies (CFB requires large amounts of fresh water) as well as ash discharge and CO2 emissions. The DFO scientists noted widespread mistrust of the provincial government's decision and that the controversial one-day hearing in January left the impression "of a cooked-up deal between the province and federal government to slip this project by without a fair assessment of its potential dangers. In fact, problems are relatively minor... Point Aconi is in some respects a model."[8]

On December 13, 1990 lawyers for Greenpeace, the Ecology Action Centre and six property owners who live near Point Aconi argued in the Federal Court of Canada that Valcourt had made a legal error in rejecting a public environmental review panel and that federal Environmental Assessment Review Panel guidelines should be followed to institute a formal review of the $436 million project. Mr. Justice Andrew MacKay ruled against the application on Friday, January 18, 1991 by stating that the Department of Fisheries and Oceans acted in accordance with the law in deciding not to order a full environmental assessment of the project. MacKay noted that the project has resulted in substantial testing of ground water around the plant. He also noted that because there are no standards for CO2, it was impossible to say that the plant would create a pollution problem with its massive CO2 emissions.[9]

A citizens liaison committee was established by Nova Scotia Power to review the project. Current (2010) Member of Parliament for Sydney—Victoria, Mark Eyking whose family operated several farms on Boularderie Island near Point Aconi was a member of this committee at that time and had questions about how emissions from the plant or ground water withdrawn for it would affect his crops or how losses would be compensated, stating "We see all these little mistakes happening and we know we're going to get dumped on. But when we ask for a neutral party to look at this, Nova Scotia power brings in its big shooters and they knock us down like pegs. Now it's almost too late but people won't sit down and take this any more."[10]

In addition to the estimated $436 million cost for the generating station, the project also included construction of a $150 million transmission line running for 435 km from Point Aconi to Halifax. Several property owners along the proposed route rejected offers by Nova Scotia Power to purchase their land, citing the physiological effects of the electromagnetic field from transmission lines. Additional controversy occurred when it was determined that the proposed route would disturb a great blue heron colony which brought angry responses from members of the Mi'kmaq Nation.[11]

Mitsui formed Mitsui & Co. (Point Aconi) Ltd. as an extraprovincial corporation in another province on December 1, 1989 as a result of its RFP submission. Mitsui & Co. (Point Aconi) Ltd. was registered in Nova Scotia on February 12, 1990 after the contract was signed with Nova Scotia Power in early January. Construction activity on the Point Aconi Generating Station began in early 1990 after Mitsui & Co. (Point Aconi) Ltd. contracted with Jones Power Corporation to act as construction manager and carry out construction work for the Point Aconi Generating Station project. Jones Power Corporation's obligations were guaranteed by its subsidiary J.A. Jones Construction.[12]

The Point Aconi Generating Station project ran into delays as a result of cost overruns, resulting in a series of prolonged contractual disputes that arose between 1991 and 1992. Jones Power Corporation claimed millions of dollars in additional compensation and a July 28, 1992 memorandum of understanding between Mitsui & Co. (Point Aconi) Ltd. and Jones Power Co. fixed compensation for Jones Power Corporation at $118 million. The companies agreed to complete the project on November 5, 1992 and leave the contractual dispute after the project's conclusion. Additional documents were discovered after the MOU had been signed but were deemed to be protected by solicitor-client privilege or litigation privilege as detailed in Mitsui & Co. (Point Aconi) Ltd. v. Jones Power Co. which is referenced as 2000 NSJ no. 258; 2000 NSCA 96; Mitsui & Co. (Point Aconi) Ltd. was removed from the Nova Scotia Registry of Joint Stock on June 23, 2003 after legal proceedings were completed.[13]

Construction of the plant was overshadowed by the resignation of Premier John Buchanan upon his appointment to the Senate of Canada in the wake of a corruption scandal relating to his tenure as premier. The selection of a new leader for the governing Progressive Conservative Association of Nova Scotia, Donald Cameron, took place on February 26, 1991. Cameron made a surprise announcement on January 9, 1992 that his government would privatize Nova Scotia Power Corporation to remove public responsibility for the utility's $2.4 billion debt; Cameron stated that the debt had hurt the province's credit rating and that there had been allegations of political interference for setting electricity rates and decisions to build large power projects.[14] The $850 million initial public offering for 85 million shares of the utility took place on August 12, 1992.[15]

The Point Aconi Generating Station began operating in March 1994 and was officially opened in a ceremony on August 12, 1994 however construction was not completed until later in the fall of 1994 and the plant didn't begin commercial operation until January 1, 1995.[16][17]

After initial production issues at the Point Aconi facility were resolved, Nova Scotia Power Corporation closed and decommissioned the 65-year-old Seaboard Generating Station in 1997.[18]

The Point Aconi Generating Station was originally designed to burn high sulphur coal mined in the Sydney Coal Field, which it sits atop. The primary source of coal was to be from the Prince Colliery, located 2 km east of the generating station property. The Prince Colliery was owned by the federal Crown corporation Cape Breton Development Corporation (DEVCO) which was beset with production problems at its three remaining collieries during the mid-late 1990s as a result of flooding, roof collapses and labour difficulties. The instability of locally mined coal forced Nova Scotia Power to import coal from the United States and South America beginning in 1998 to supplement the supply from DEVCO.[19]

From 1998–2000, Nova Scotia Power brought imported coal into Nova Scotia at the Martin Marietta Materials aggregate loading facility in Auld's Cove, Nova Scotia on the [[Strait of Canso. This required coal ordered for the Point Aconi Generating Station and Lingan Generating Station to be transported by the Cape Breton and Central Nova Scotia Railway to the DEVCO coal washing plant at Victoria Junction, whereby the coal destined for the Point Aconi Generating Station was trucked the final distance to the plant. DEVCO closed the Prince Colliery, its last operating coal mine, on November 23, 2001; ironically, the original reason for constructing the Point Aconi Generating Station had been to secure the long-term viability of the Prince Colliery.[20]

After Nova Scotia Power purchased the surface assets of DEVCO in late 2001, all coal for its two remaining thermal generating stations in Industrial Cape Breton was imported through the International Coal Pier on Sydney Harbour which was formerly owned and operated for coal export by DEVCO.[21]

Operation

The plant burns coal and petroleum coke, which is transported to the facility using dump trucks from a bulk ship unloading pier in Sydney Harbour near the community of Whitney Pier.

It features one boiler and one chimney 107-metres above ground.

The Point Aconi Generating Station consumes 189,000 tonnes of coal and 213,000 tonnes of petroleum coke per year and currently generates approximately 6.8% of the province's electricity and produces roughly 10.07% of the province's air pollution, including hydrochloric acid, sulphuric acid, hexachlorobenzene and mercury.[22] In 2007 it created 1.465 million tonnes of greenhouse gases.[23]

Project Details

  • Sponsor: Nova Scotia Power Corporation
  • Parent Company: Nova Scotia Power Corporation
  • Location: Point Aconi, Nova Scotia, Canada
  • Coordinates: 46.321633, -60.329987 (exact)
  • Status: Operating
  • Capacity: 165 MW
  • Type: Circulating fluidized bed (20% fired by coal, 80% by petcoke)
  • Start date: 1993
  • Coal Type: Bituminous
  • Coal Source:
  • Source of financing:

Resources and articles

References

  1. Point Aconi Generating Station, Wikpedia, accessed May 2019
  2. Nova Scotia Power’s Point Aconi plant overcomes CFB design problems to become rock of reliability, Powermag, Sep. 15, 2006
  3. "Buchanan short-circuits N.S. utilities board with power plant bill." The Globe and Mail, Thursday, April 27, 1989
  4. Kevin Cox "Panel asked to show evidence power plant hearing not 'sham'." The Globe and Mail, Friday, January 19, 1990
  5. Kevin Cox "Nova Scotia to construct a coal-fired power plant" The Globe and Mail, Saturday, March 10, 1990
  6. Kevin Cox "Nova Scotia to construct a coal-fired power plant" The Globe and Mail Saturday, March 10, 1990
  7. Archived copy. Archived from the original on 2007-12-14. Retrieved on 2010-04-26. Canada-United States Clean Air Agreement - Environment Canada
  8. Kevin Cox "Ottawa rejects full review of power station's effects." The Globe and Mail Friday, September 21, 1990
  9. Special to the Globe and Mail "Lawyer contends minister erred in coal plant ruling" The Globe and Mail Friday, December 13, 1990
  10. Kevin Cox "Power but no glory in Point Aconi" The Globe and Mail Saturday, March 16, 1991
  11. Kevin Cox "Power plant ruffles more than feathers" The Globe and Mail Saturday, July 6, 1991
  12. https://rjsc.gov.ns.ca Nova Scotia Registry of Joint Stock
  13. Walker, Janet (2005). The Civil Litigation Process: Cases and Materials, Sixth Edition. Toronto: Emond Montgomery Publications Limited, pg. 826
  14. Kevin Cox "N.S. to sell off electrical utility: Premier sets June stock sale." The Globe and Mail Friday, January 10, 1992
  15. Dennis Slocum "N.S. Power share offering a sellout." The Globe and Mail Thursday, August 13, 1992
  16. "N.S. Power earnings off." The Globe and Mail Saturday, August 13, 1994
  17. "Aconi generates more jobs, less flak: Power plant officially opened, but still not ready." The Chronicle Herald Saturday, August 13, 1994
  18. "Seaboard Power Corporation" taken from History of Electric Power Companies in Nova Scotia
  19. "NSP to Import More U.S. Coal: Coal Shortage Shuts Down Generating Plant" Cape Breton Post October 23, 1998 taken from History of Nova Scotia with special attention given to Communications and Transportation, Chapter 40, September-October 1998
  20. "Pennsylvania Coal Unloaded at Sydney" Cape Breton Post October 23, 1998 taken from History of Nova Scotia with special attention given to Communications and Transportation, Chapter 40, September-October 1998
  21. http://www.littletechshoppe.com/ns1625/nshist50.html "NSPI Fuel Supplies at Dangerously Low Levels" Nova Scotia Power (http://www.nspower.ca/AboutUs/WhatsNew/detail1568.html)
  22. "Dirty Air from Power Plants Fuels Health Problems in Nova Scotia" Pollution Watch
  23. Facility and Greenhouse Gas Emissions, Environment Canada, 2007

Related SourceWatch articles

External resources

External articles

Wikipedia also has an article on Point Aconi Generating Station (Point Aconi Generating Station). This article may use content from the Wikipedia article under the terms of the Creative Commons Attribution-ShareAlike 3.0 Unported License.