Rapid Pengerang power station

From SourceWatch
Jump to navigation Jump to search
Part of the Global Gas Plant Tracker, a Global Energy Monitor and Center for Media and Democracy project.

Rapid Pengerang power station (also known as Pengerang Co-generation Plant) is a 1,900-megawatt (MW) gas-fired power plant in the state of Johor, Malaysia.[1]

Location

The below satellite image shows the location of the power station in Pengerang, Johor, Malaysia.

Loading map...

Background

Occupying an area of approximately 6,242 acres, the Pengerang Integrated Complex (PIC) is the largest project ever undertaken by Malaysia's national oil and gas company, PETRONAS, and is the largest single construction project in the country of Malaysia.[2] PIC consists of the Refinery and Petrochemical Integrated Development (RAPID) and six associated facilities: Re-gasification Terminal 2, a raw water supply project, an air separation unit, the Pengerang Deepwater Terminal, centralized and shared utilities and facilities, and the Pengerang Co-generation Plant (PCP).[3]

The Pengerang Co-generation Plant's first co-generating unit achieved a commercial operation date of October 2017, while its last unit went into operation in late-December 2018.[4][1]

Both the Pengerang Co-generation Plant and the PIC form part of the Johor State’s Pengerang Integrated Petroleum Complex (PIPC), which is under Malaysia’s Economic Transformation Programme (ETP) to establish new engines of growth for Malaysia.[5]

Project Details

  • Sponsor: Pengerang Power Sdn. Bhd.[6]
  • Parent company: Petroliam Nasional Bhd. (PETRONAS)
  • Location: Pengerang, Johor, Malaysia
  • Coordinates: 1.3769, 104.1743 (exact)
  • Gross capacity (operating): 1,900 MW[1]
    • Combined-cycle units 1-4: 475 MW per unit

Articles and Resources

References

  1. 1.0 1.1 1.2 "The Pengerang Cogeneration Plant Milestone" Siemens Malaysia, Jan. 15, 2019.
  2. Fluor Projects Fluor Corporation, accessed November 2019.
  3. The Projects PETRONAS, accessed November 2019.
  4. "Pengerang Cogeneration Plant Achieves First COD" PETRONAS, Oct. 22, 2017.
  5. "PETRONAS Kicks off Its Pengerang Co-generation Power Plant" PETRONAS, Nov. 3, 2014.