Shanxi Coal Hequ power station
{{#badges:CoalSwarm|Navbar-Chinacoal}} The Shanxi Coal Hequ power station (山西焦煤中机国能山煤河曲能源公司) is a proposed 700-megawatt (MW) coal-fired power station in Shanxi province, China.
Shanxi Coal International Energy Group has also announced that a 350 MW coal plant employing carbon capture and storage technology will be built in Taiyuan. It is not known whether that plant will share the same location.
Contents
Location
The undated satellite photo below shows the proposed location for the plant in Xinzhou city.
Background on Plant
Shanxi Coal International Energy Group has proposed a power station of two units of 350 MW each. The environmental impact assessment was approved in 2014.[1][2][3]
The power station is under construction and planned for 2017.[4]
2017: Plant halted by government
In July 2017, the NEA released the "Guideline of Supply-Side Reform of the Coal Power Bubble". The Guideline included a draft list which slowed down or halted 185 coal-burning units across 21 provinces, totaling 107 GW. 114 coal units (65 GW) are ordered to slow down the construction progress during 2017 to 2020, and are not allowed to connect to the grid in 2017. In addition, 71 coal units (42 GW) were halted indefinitely for regulation violations. The list partly overlapped with the projects listed in the January NEA letter to 13 provinces.[5]
Shanxi Coal Hequ power station Units 1-2 are among the halted coal-burning units,[5] and also appeared on an updated list of halted projects released in September 2017.[6]
For more information, see China's 2016/2017 Restrictions on Development of Coal-Fired Power Capacity.
CCS plant
Shanxi Coal International Energy Group has also announced that a 350 MW coal plant employing carbon capture and storage technology will be built in Taiyuan. It is not known whether that plant will share the same location.[7]
Project Details
- Sponsor: Shanxi Coal International Energy Group
- Parent company: China Sinogy Electric Group, Shanxi Coking Coal Group
- Location: Xinzhou city, Hequ county, Shanxi province, China
- Coordinates: 39.111156, 111.182432 (exact)
- Status: Shelved (construction halted by government policy in July 2017)
- Gross capacity: 700 MW (Units 1-2: 350 MW)
- Projected in service:
- Type: Ultra-supercritical
- Coal type: Waste coal
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "山煤集团河曲低热值煤发电项目获得核准," 山西新闻网--山西经济日报, 2014-08-01
- ↑ "山煤河曲2X350MW低热值煤电厂项目召开股东会议," Shanxi Coal Imp. & Exp. Group, 2014-8-4
- ↑ "山西省重大项目办调研山煤集团河曲低热值煤发电项目," 中国火力发电网, 2015-05-08
- ↑ "山煤河曲2×35万千瓦低热值煤发电项目正式开工," 10/24/2015
- ↑ 5.0 5.1 "16部委联合发文防范化解煤电产能过剩风险," Sohu.com, 2017-08-03
- ↑ "2017年分省煤电停建和缓建项目名单," Sohu, 2017-10-12
- ↑ "Shanxi International Energy Group CCUS Project," Global CCS Institute, accessed December 2014