{{#badges:CoalSwarm|Navbar-Chinacoal}}Shanxi Hepo power station (山西国际能源河坡发电) is a 700-megawatt (MW) coal-fired power plant in Shanxi Province, China.
Contents
Location
The map below shows the location of the plant in South Street of Yangquan Prefecture, Shanxi Province.
The map below shows the location of the expansion in Xiayan Village, Mengying Town, Jiao District, Yangquan Prefecture, Shanxi Province.
Background on Plant
The four existing coal-fired units of Shanxi Hepo power station, totaling 300 MW, were brought online between 1991 and 2000. The plant is owned by Shanxi International Electricity Group.[1]
The 4 units were retired in 2016 after the expansion units went operation.[2]
Description of Expansion
Shanxi International Electricity Group is currently building two additional coal-fired units at this plant, with a total planned capacity of 700 MW. The new units are scheduled to be completed in 2015.[3][4]
The new units were completed in 2016.[5]
Project Details for Units 5 & 6 Expansion
- Sponsor: Shanxi International Energy Group (93.5%), Yangquan Asset Management Investment (6.5%)
- Location: Xiayan Village, Mengying Town, Jiao District, Yangquan Prefecture, Shanxi Province, China
- Coordinates: 37.919943, 113.615236(exact)
- Status: Operating
- Gross capacity: 700 MW (Units 5 & 6: 350 MW)
- Type: Supercritical
- Projected in service: 2016
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "关于山西河坡发电有限责任公司“上大压小”热电联产异地新建工程(变更)补充环境影响报告书的批复", 中华人民共和国环境保护部, 2014-04-14
- ↑ "山西河坡发电有限责任公司企业简介," International Energy Group, accessed Jan 2018
- ↑ "山西河坡电厂2×350兆瓦超临界热电联产项目开工", 阳泉市政府, 2012-09-24
- ↑ "山西河坡发电公司北侧大门及煤场管理站建筑安装工程招标," 015-06-10
- ↑ "[独家2016年12月电力项目情况:涉及核准、开工、并网等,"] Sohu, Jan 10, 2017