==Background on Plant==
In October 2010 Intos INC., Infinite Computer Solution (India) and Eldeco Housing & Industries Ltd together proposed to invest Rs.30 billion to set up a 600 MW plant in Murka. Creative Thermolite Power Pvt Ltd was formed as a special purpose vehicle (SPV) to implement the project.<ref name=cmie>[http://www.cmie.com/kommon/bin/sr.php?kall=wclrdhtm&nvdt=20131212111408040&nvpc=099000000000&nvtype=TIDINGS "Extension granted to 9 power projects in UP,"] Centre for Monitoring Indian Economy Pvt. Ltd., Dec 12, 2013.</ref>
 
The project was expected get commissioned by end of 2014, but has not secured environmental clearance or a coal linkage, and was given an 18-month extension on its terms of reference in December 2013.<ref name=cmie/>
==Project Details==
*'''Coordinates:''' 25.1996699, 81.5021825 (approximate)
*'''Status:''' Pre-permit development
*'''Capacity:''' **Unit 1: 300 MW**Unit 2: 300 MW
*'''Type:'''
*'''Start date:'''