Tanjung Jati B power station

From SourceWatch
Jump to navigation Jump to search

{{#badges: CoalSwarm|Navbar-Indonesiacoal}}Tanjung Jati B power station (also known as Jawa-4) is a 2,640 megawatt (MW) coal-fired power station in Central Java Province, Indonesia. An additional 2 x 1000 MW is under development.[1]

Tanjung Jati B Phase I and Phase II Location

The satellite photograph below shows the Tanjung Jati B power station, which is located at Tanjung Jati, Kembang District, Jepara Regency, Central Java Province, Indonesia.

Loading map...

Tanjung Jati B Phase III Location

The satellie photograph below shows the Phase III expansion being built to the east of the Tanjung Jati B power station.

Loading map...

Background

Tanjung Jati B power station is a 2,640 megawatt (MW) coal-fired power station located in Central Java Province, Indonesia. The power station comprises four 660 MW generating units.[2][3] Tanjung Jati Coal Terminal serves the power station.[4]

The current plant was built in two phases, each comprising two 660 MW units. A third phase of two 1,000 MW units is planned. The project owner, PT Central Java Power (owned by Sumitomo) has executed a finance lease agreement with PT PLN as the lessee. When the lease period expires the assets will be transferred to PLN.[5]

Phase I (Units 1 and 2): 2 x 660 MW

The first phase went through a long history of development before finally being commissioned in 2006. The website "Power Plants Around the World" describes the story as follows:[6]

" Tanjung Jati-B was proposed by Hopewell Holdings and initially bid as an IPP in June 1994. A PPA with PLN followed in September 1994. The EPC contract was signed in September 1995 and site work started on 15 April 1997. The Asian financial crisis combined with allegations about mismanagement of the PPA terms led to Hopewell withdrawing, leaving the project about one-third complete. Sumitomo renegotiated the development as a leasing scheme and construction resumed in September 2003 with financing from JBIC. The 5-year project suspension led to parts and equipment being stored onsite and at 75 locations worldwide."

Phase II (Units 3 and 4): 2 x 660 MW

Unit 3 was commissioned in November 2011 and Unit 4 was commissioned in January 2012. The units cost $2.1 billion.[2]

Phase III (Units 5 and 6): 2 x 1000 MW

A third phase of two 1000 MW units is described in PLN's long-range plan for 2013-2022. It is referred to as "PLTU Jawa-4 #5 and #6" and is slated for 2019 and 2020. [7][8]

In December 2013, the government of Jepara Regency renewed its push for the two units to be built. Outstanding issues that that point included lining up investors, land acquisition, building a new transmission line, and lining up government support.[9]

As of March 2015, the plant's proponents were holding public hearings as part of the EIA environmental permit application process. Sumitomo said it hoped to complete the units by 2019.[10]

PLN's long-range plan for 2016-2025 included Jawa-4 as a 2,000 MW addition in 2019.[11] Sumitomo announced in December 2015 that a power purchase agreement had been signed for two units of 1,000 MW each. According to Sumitomo, the company along with Kansai Electric Power and PT United Tractors (an affiliate of Indonesian conglomerate Astra Group) signed the agreement with PT PLN (Persero) on December 21, 2015.[12]

In February 2016, RambuEnergy reported that an environmental impact study, also known as an "Amdal study," for the two projects had been underway since the previous year. The head of the Amdal study team said that the study might be completed by the end of February. Governor Pranowo said that growing electricity demand in Central Java made the project crucial. The RambuEnergy article described the units as 1,070 MW each and described the combustion technology as ultra-supercritical. According to the article, local NGOs were calling on the government to postpone the Amdal document. A spokesperson for the United Jepara Forum (Forum Jepara Bersatu/FJB) said that the document needed further clarity.[13]

The projects is a BOT (Build, Operate and Transfer) scheme of 25 years, after which it will be transfered to PT PLN. The total project cost is expected 500 billion yen, mainly funded by project finance.[12] In February 2017, the financing for the plant was US$3.355 billion.[14]

In March 2017, industri.bisnis.com reported the signing of a statement and guarantee document by PLN and BJP, described as a key part of the pre-financial close phase. PLN and BJB had previously. In December 2015 the two parties signed a power purchase agreement (PPA), and they amended the PPA in September 2016.[15]

In August 2017 it was reported that construction had begun on the units, with completion planned for 2021.[16] In August 2018 it was reported that construction was 32% complete.[17] In May 2019 it was reported that construction was at 55%-60% and that Unit 5 and Unit 6 would be commissioned in September 2021.[18] In July 2019 it was reported that construction of Unit 5 and Unit 6 was 75% complete.[19]

Public opposition

At a public hearing in Tubanan Village in March 2015, local fishermen spoke out strongly against the proposed plant. They argued that the company had failed to live up to the standards that it had set in the EIA for Units 3 & 4 in 2007. One complaint was that the plant's owners had failed to put a filter on the water intake as promised, with the result that small fish were getting sucked in and killed.[20]

Waste issues

The plant has had problems with waste disposal. Waste was originally being moved out of the plant via truck, but locals complained that the trucks were damaging local roads. The company then started transporting waste by barge, but fishers were worried that leaking waste would impact fish stocks. The company has only a limited amount of space onsite to store waste, and was concerned that the plant would have to shut down.[21]

Coal

For the existing plant, PLN concluded a coal deal in April 2017 with PT Indominco Mandiri and PT Kaltim Prima Coal (KPC) under which the plant will receive 4.8 million tonnes of coal per year for 5 years. The coal is 5,500-5,700 kcal/kg, i.e. bituminous coal. Units 5 and 6 will require an additional 7 million tonnes per year.[22]

Project Details for Phases II & III Expansions

  • Sponsor: PT Bhumi Jati Power (BJP)
  • Parent company: Sumitomo Corporation, Kansai Electric Power Co. and PT United Tractors (part of Astra Group conglomerate)[12]
  • Arrangement: Build, operate, transfer (25 years)[12]
  • Location: Tanjung Jati, Kembang District, Jepara Regency, Central Java Province, Indonesia
  • Coordinates: -6.446488,110.742359 (exact)
  • Status: Phase II: Operating; Phase III: Construction
  • Gross Capacity: Phase II: 1320 MW (Units 3 & 4: 660 MW); Phase III: 2,140 (Units 5 & 6: 1,000 MW)[12][13]
  • Type: Subcritical (Phase II), Ultra-supercritical (Phase III)
  • Project In service: 2011 (Phase II Unit 3); 2012 (Phase II Unit 4); 2021 (Phase III)
  • Coal Type: Subbituminous
  • Coal Source:
  • Source of financing:
    • Phase II: Japan Bank for International Cooperation (JBIC) and co-financing by Bank of Tokyo-Mitsubishi UFJ, Sumitomo Mitsui Banking Corp and BNP Paribas.[2]
    • Phase III: Japan Bank for International Cooperation (JBIC) and co-financing by Mizuho Bank, Ltd., Sumitomo Mitsui Banking Corporation, The Bank of Tokyo-Mitsubishi UFJ, Ltd., Sumitomo Mitsui Trust Bank, Limited, Mitsubishi UFJ Trust and Banking Corporation, The Norinchukin Bank and Singapore's Oversea-Chinese Banking Corporation Limited.[14]

Articles and resources

References

  1. "Pengembangan Pembangkit 35.000 MW dan Kesiapan Infrastruktur Sistem Jawa Bali," presentation by E. Haryadi, PT PLN, 19 August 2015
  2. 2.0 2.1 2.2 "Tanjung Jati-B Coal Power Plant Indonesia," Global Energy Observatory, accessed December 2013
  3. "Coal-Fired Plants Financed by International Public Investment Institutions Since 1994", Appendix to Foreclosing the Future: Coal, Climate and International Public Finance: Investment in coal-fired power plants hinders the fight against global warming, Environmental Defense, April 2009.
  4. "Indonesia Coal Ports" Censin Resources, accessed on August 16, 2011.
  5. "Outline of Jati-B Power Generation Project," Sumitomo Corporation, accessed December 2013
  6. "Coal-Fired Power Plants in Indonesia," Power Plants Around the World, accessed December 2013
  7. “PLN Long Term Electricity Plan (2013-2023),” presentation by Moch. Sofyan, Head of New & Renewable Division of PT PLN (Persero), 06 March 2014, p. 11
  8. Muhammad Oliez, "PLTU Tanjung Jati B unit 5 dan 6 mendesak dibangun" (Tanjung Jati B power plant units 5 and 6 urgent constructed), SindNews.com, December 3, 2013
  9. Muhammad Oliez. PLTU Tanjung Jati B unit 5 dan 6 mendesak dibangun. Sindo News, 3 Dec. 2013.
  10. Konsultasi Publik AMDAL Pembangunan dan Pengoperasian Unit 5&6 PLTU TJB, Suara Online Terkini, 3 Mar. 2015.
  11. “Rencana Usaha Penyediaan Tenaga Listrik, PT PLN (Persero), 2016-2025,” Kementerian Energi Dan Sumber Daya Mineral, June 2016
  12. 12.0 12.1 12.2 12.3 12.4 "Tanjung Jati B coal-fired power plant Unit 5 & 6 Expansion Project (2,000MW)," Sumitomo, December 21, 2015
  13. 13.0 13.1 "Development of Tanjung Jati B Unit 5 & 6 in Central Java drags on," RambuEnergy, February 24, 2016
  14. 14.0 14.1 "Project Finance for Re-expansion of Tanjung Jati B Coal-Fired Power Plant in Indonesia," JBIC announcement, 27 February 2017
  15. "PLN Accelerates Development of Tanjung Jati B," industri.bisnis.com, 28 March 2017
  16. "Jawa 4 Power Plant to Begin Operations in 2021," Tempo, Sep 5, 2017
  17. Komang Berharap PLTU Tanjung Jati B Unit 5 dan 6 Rampung 2021, Tribun Jateng, Aug. 9, 2018
  18. PLTU Tanjung Jati B Jepara Siap Beri Pasokan Listrik 4,640 Mw, Suara Merdeka, May 16, 2019
  19. Salip Paiton, Tanjung Jati B Siap Jadi PLTU Terbesar di Indonesia, Semarang, Jul. 31, 2019
  20. Nelayan Jepara Tolak Pembangunan Unit 5 dan 6 PLTU Jepara, Berita Jateng, 3 Mar. 2015.
  21. PLTU Tanjung Jati B Jepara Terancam 'Off', Liputan 6, 18 May 2013.
  22. Michael Agustinus, "Pasokan Batu Bara untuk PLTU Tanjung Jati B Dipastikan Aman," delikFinance, 16 May 2017

Related SourceWatch articles

External resources

External articles