{{#badges:CoalSwarm|Navbar-Chinacoal}}Weiqiao Huji power station (魏桥集团惠民胡集电厂) is a 2,640-megawatt (MW) coal-fired power plant in Shandong Province, China.
Contents
Location
The undated satellite photo below shows Units 1-4 of the power station in Huji Town.
Loading map...
The satellite photo below shows Units 5-8.
Loading map...
Background on Plant
Weiqiao Huji power station is a 4 x 330 MW subcritical coal plant at Binzhou prefecture, owned by Shandong Weiqiao Group. Units 3-4 began operating in 2014.[1] Units 1-2 were completed in 2015.[2][3]
Proposed expansion
Shandong Weiqiao Group is constructing an additional units 5-8 at the power station, totaling 1,320 MW (four units of 330 MW each).[4]
The units were commissioned in 2016.[5][6]
Project Details of units 1-4
- Sponsor: Weiqiao Huimin New Material Co.
- Parent company: Shandong Weiqiao Group
- Location: Huji Town, Huimin County, Binzhou prefecture, Shandong Province, China
- Coordinates: 37.347901, 117.781587 (exact)
- Status: Operating
- Gross capacity: 1,320 MW (Units 1-4: 330 MW)
- Type: Subcritical
- In service: 2014 (Units 3-4), 2015 (Units 1-2)
- Coal type:
- Coal source:
- Source of financing:
Project Details of units 5-8
- Sponsor: Weiqiao Huimin New Material Co.
- Parent company: Shandong Weiqiao Group
- Location: Huji Town, Huimin County, Binzhou prefecture, Shandong Province, China
- Coordinates: 37.3594471, 117.7770746 (exact)
- Status: Operating
- Gross capacity: 1,320 MW (Units 5-8: 330 MW)
- Type:
- In service: 2016
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "魏桥胡集电厂项目4号机组完成168小时满负荷试运行," 中国火力发电网, 2014-08-27
- ↑ "环境保护部公告," China MEP, 2015年06月23日
- ↑ "努力开拓 不断进取: 公司胡集4*350MW2#机组电仪安装开工," 2015-8-27
- ↑ "山东惠民县胡集电厂二期工程开工建设," aladdiny.com, 2014/9/22
- ↑ "【基层动态】山东分公司胡集项目7号机组正式投入商业运营," Sep 26, 2016
- ↑ "山东胡集电厂二期工程8号锅炉汽包正式安装就位," 中国电力化工网, 2016-03-03