Xinjiang Guoxin Qitai power station
{{#badges:CoalSwarm|Navbar-Chinacoal}} Xinjiang Guoxin Qitai power station (新疆国信煤电能源公司准东发电厂) is a proposed 1,320-megawatt (MW) coal-fired power plant in Xinjiang Uyghur Autonomous Region, China.
The project appears to have a different location and sponsor than the nearby Xinyou Qitai power station.
Contents
Location
The photo below shows the proposed location for the plant in Qitai County. Planet satellite photos show significant construction progress through February 2018.
Background on Project
Xinjiang Guoxin Coal Power Company has proposed a power station of two units of 660 MW for Changji city. The environmental impact assessment was approved in 2014,[1] although the power station was reported as under construction in 2013.[2]
It was planned for operation in 2016,[3] but unit 1 was not commissioned until January 2018.[4]
Project Details
- Sponsor: Xinjiang Guoxin Coal Power Company
- Parent company: GCL Poly Energy Holdings (81%), China Resources (19%)
- Location: Changji city, Qitai County, Xinjiang Uyghur Autonomous Region, China
- Coordinates: 44.362817, 90.152276 (exact)
- Status: Operating (Unit 1), Construction (Unit 2)
- Gross capacity: 1,320 MW (Units 1-2: 660 MW)
- Type: Supercritical
- Start year: 2018
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "关于新疆国信准东2×660MW煤电项目工程环境影响报告书的批复," MEP, September 16, 2014
- ↑ "新疆国信煤电能源公司2×66万千瓦煤电项目在奇台开工建设," 昌吉日报, 2013-05-09
- ↑ "国信煤电能源准东2×66万千瓦电厂项目获自治区核准," 新疆能源网, 2015年05月18日
- ↑ "新疆国信准东煤电项目1号机组通过168试运," 北极星电力网新闻中心, 2018/1/23