{{#badges:CoalSwarm|Navbar-Chinacoal}}Yichang Xiaoting power station (华润电力宜昌公司) is a 700-megawatt (MW) coal-fired power plant in Hubei Province, China.
Contents
Location
The map below shows the plant, in Xiaoting District, Yichang Prefecture, Hubei Province.
Loading map...
Background on Project
China Resources has proposed a two-unit coal-fired power plant with a total planned capacity of 700 MW in Hubei Province. The plant went online in 2014.[1]
Project Details
- Sponsor: China Resources
- Location: Xiaoting District, Yichang Prefecture, Hubei Province, China
- Coordinates: 30.4969793, 111.4419115 (exact)
- Status: Operating
- Gross capacity: 700 MW (Units 1 & 2: 350 MW)
- Type: Supercritical
- Projected in service: 2014
- Coal type:
- Coal source:
- Source of financing:
Articles and resources
References
- ↑ "华润宜昌热电项目全面投产", 华润(集团)有限公司, 来源:三峡日报, 2014-06-03