Enbridge Line 5 Oil Pipeline
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor and the Center for Media and Democracy. |
Sub-articles: |
Enbridge Line 5 is a major oil pipeline in the Enbridge Pipeline System, which conveys petroleum from western Canada to eastern Canada via the Great Lakes states. Line 5 is particularly notable for passing under the environmentally sensitive Straits of Mackinac, which connect Lake Michigan to Lake Huron. The 645-mile, 30-inch diameter pipeline is capable of carrying up to 540,000 barrels of oil per day.[1] It carries synthetic crude, natural gas liquids, sweet crude, and light sour crude.[1]
Contents
Location
The pipeline originates in Superior, Wisconsin, travels through the Upper and Lower Peninsulas in Michigan, and terminates in Sarnia, Ontario.
Project Details
- Operator: Enbridge
- Current capacity: 540,000 barrels per day
- Length: 645 miles (1,038 kilometers)
- Status: Operating
- Start Year: 1953
Route
The pipeline runs between two major nodes of the Enbridge Pipeline System at Superior, Wisconsin, and Sarnia, Ontario. The Enbridge terminal at Superior conveys western Canadian crude oil from various incoming pipelines (including lines 1–4) to Line 5 and Line 6, which go around the northern and southern shores of Lake Michigan, respectively.
From Superior, Line 5 travels east to the Upper Peninsula of Michigan, then runs southeast to Rapid River, near Escanaba. At Rapid River, natural gas liquids (NGL) are side stream delivered for stripping, and the stripped NGLs are reinjected.[2]
From Rapid River, the pipeline runs near the northern shore of Lake Michigan until it reaches the Straits of Mackinac. There the pipeline divides into two separate 20-inch lines, which reunite when they reach the southern side of the straits.[2] The lines are buried until they reach a depth of convert 65 feet.[3] The lines descend to a depth of approximately 270 feet under the straits.
Once on land again in the Lower Peninsula, Line 5 runs near Interstate 75 to Bay City, Michigan.[4] At the Lewiston pumping station, US sweet crude may be injected.[2] From Lewiston, Line 5 loops around Saginaw Bay, then runs southeast to the St. Clair River.
Just before the St. Clair River, Line 5 reaches the Marysville pumping station. Volumes destined for Michigan and Ohio refineries such as BP-Husky Refinery and Marathon Detroit Refinery are offloaded there,[2] and transferred to a Sunoco pipeline that runs from Marysville to Toledo.[5]
The line then proceeds east across the St. Clair River to Ontario, where it rejoins Enbridge Line 6 and terminates at Sarnia.[6] Any volumes not destined for Sarnia-area refineries are there pumped into tanks for transfer to Enbridge Line 7.[2]
Background
Construction on Line 5 was completed in 1953.[1] The pipelines from western Canada to Superior had been completed in 1950; prior to the construction of Line 5, the crude oil was conveyed from Superior to southern Ontario by oil tankers.[7]
In 2013, the line's capacity was increased by 50,000 barrels per day, from 490,000 to 540,000 barrels.[8] The upgrade involved US$100 million in improvements to pumping stations, but no change to the actual pipes.[9]
Opposition
The 2013 expansion, coupled with the anticipated expansion of the Alberta Clipper pipeline, led to concerns from the National Wildlife Federation and other groups over the possible shipment of diluted bitumen from the Alberta tar sands through Line 5.[10] However, Enbridge has denied any plans to pump such materials. A 2011 toll agreement describes the materials as "condensate, light synthetic, sweet, light sour and NGL,"[2] as does a 2013 summary of the Mainline System.[2] Due to national security concerns, however, the Pipeline and Hazardous Materials Safety Administration does not divulge the materials actually carried on major US pipelines, including Line 5.[10]
Public concerns have particularly focused on the risk of a spill under the Straits of Mackinac, and the difficulty of controlling any spill that might occur.[8] According to Enbridge, the pipes under the straits have never leaked, are monitored 24 hours a day, and are regularly inspected by underwater autonomous vehicles.[1] However, there have been numerous spills elsewhere in Michigan from Enbridge pipelines, including a major Line 5 spill at Crystal Falls, Michigan in 1999, as well as the 2010 Kalamazoo River oil spill on Line 6.[10] Line 5 has spilled 29 times and at least 1.1 million gallons along its length since 1968. Enbridge’s pipelines, which run about 1,000 feet apart at depths ranging from 100 - 270 feet, have laid on the bottom of the Straits for more than six decades. Enbridge installed several support structures under the pipelines in 2006 and again in 2010, following the company’s oil spill into the Kalamazoo River - the nation’s largest-ever land-based oil spill. The pipelines in the Straits of Mackinac cross one of the most ecologically sensitive areas in the world. The Great Lakes are home to 20 percent of the fresh surface water on the planet. University of Michigan scientists modeled the currents in the Straits of Mackinac and called it "the worst possible place for an oil spill in the Great Lakes." Despite these risks, Enbridge submitted a plan to build a tunnel for Line 5 under the Straits of Mackinac. This would keep oil flowing and Great Lakes at risk for a spill for several years, and would most certainly open the door for Enbridge to upgrade the entire pipeline to carry toxic tar sands oil - the dirtiest fossil fuel with the biggest contribution to climate change.[11]
By the end of 2015, eight Michigan counties or municipalities were calling for the retirement of Line 5 including Cheboygan, Cheboygan County, Emmet County, Genesee County, Mackinaw City, Mentor Township, Munising Township, and Wayne County.[12]
In August 2017, Michigan Governor Rick Snyder said he was "greatly concerned" about revelations by Enbridge confirming at least two areas of the pipeline under the Straits of Mackinac had lost their protective coating used to prevent corrosion down to bare metal.[13] The revelation came after years of denials by Enbridge that there were any portions of the pipeline that had lost protective coating down to bare metal.[14] The Michigan Agency for Energy, Michigan Department of Environmental Quality (DEQ), Michigan Department of Natural Resources (DNR), and the Michigan State Police echoed the concern in a press release calling for the immediate inspection of areas around every anchor on Line 5, a report to the DNR and DEQ of any findings from the inspections, a copy of the video of the recent work performed on the pipeline, and repair within 30 days of any damage to the pipeline’s coating.[15]
Another area of opposition has focused on 12 miles of Line 5 that cross through the Chequamegon-Nicolet National Forest.[16] As of September 2017, Enbridge was working with the US National Forest Service to renew a special use permit for the section, which expired in 2013.[16] Enbridge characterized the permit expiration as an "oversight" stemming from staff turnover in a 2014 letter to Forest Service.[16]
Governor Gretchen Whitmer, who replaced Governor Rick Snyder in a 2018 election, ran on a platform that supported shutting down the Enbridge Line 5. Michigan Attorney General Dana Nessel, a fellow Democrat who also campaigned on shutting down Line 5, said legislation to allow for construction of the $350 million to $500 million tunnel, approved during the lame-duck session during the last days of the administration of Republican Gov. Rick Snyder, violates the state constitution. Critics say that the line mostly moves Canadian oil to Canadian markets, and there are other ways to deliver propane to Michigan's Upper Peninsula, and the Great Lakes would continue to face unacceptable risk of a catastrophic spill during the roughly 10 years it's expected to take to construct the tunnel. As of April 2019, it is unclear who will make the next move, the Whitmer administration shutting down the pipelines, or Enbridge appealing the administration's decision in the courts.[17]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 About Line 5, Enbridge, accessed September 2017
- ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 Enbridge Pipelines Inc. (July 1, 2011). Competitive Toll Settlement. Retrieved on March 30, 2014.
- ↑ Line 5 Underwater Images. Enbridge. Retrieved on March 31, 2014.
- ↑ Sherburne, Morgan (July 12, 2013). "Enbridge to Increase Oil Flow under Straits, Rally Planned", Petoskey News. Retrieved on March 31, 2014.
- ↑ Crude Oil Pipeline System. Sunoco. Retrieved on April 1, 2014.
- ↑ Pipeline System Configuration: Quarter 1, 2013. Enbridge (2013).
- ↑ Simonson, Mike (January 25, 2013). "Bakken Boom Has Calumet Considering Building Oil Loading Dock in Superior", BusinessNorth. Archived from the original on April 7, 2014.
- ↑ 8.0 8.1 Template:Cite press release
- ↑ Enbridge to increase oil flow under Straits, rally planned, Petoskey News, 12 Jul. 2013
- ↑ 10.0 10.1 10.2 Leahy, Derek (March 6, 2014). "Concerns Mount About 61-Year Old Enbridge Pipeline in the Great Lakes", Desmog Canada. Retrieved on March 31, 2014.
- ↑ The Problem Oil and Water Don't Mix, accessed April 2019
- ↑ Oil & Water Don't Mix (2015) "Local governments are issuing resolutions calling for the shutdown of the flow of oil in Line 5 at the Straits of Mackinac"
- ↑ Line 5 bare metal exposed in coating gaps, Enbridge confirms, M Live, 30 Aug. 2017
- ↑ Outer wrap coating has failed on parts of Line 5, Enbridge confirms, M Live, 14 Mar. 2017
- ↑ State agencies call for immediate repair of damage to coating on Straits pipeline, Michigan Department of Natural Resources, 30 Aug. 2017
- ↑ 16.0 16.1 16.2 Pipeline protest takes new approach: Enbridge’s Line 5 latest to be scrutinized West Fargo Pioneer, 1 Sep. 2017
- ↑ Here's what's next in fight over Enbridge Line 5 pipeline in Straits of Mackinac Detroit Free Press, accessed April 2019
Related SourceWatch articles
External resources
Wikipedia also has an article on Enbridge Line 5. This article may use content from the Wikipedia article under the terms of the GFDL.