Matarbari power station
This article is part of the CoalSwarm coverage of Bangladesh and coal | |
Sub-articles: | |
| |
Related articles: | |
The Matarbari power station is a proposed 1200 megawatt (MW) coal-fired in Matarbari, Cox's Bazar, Chittagong, Bangladesh. It is one part of the broader Maheshkhali power complex plan that includes several proposed coal and gas-fired plants.
A phase II of 1200 MW is proposed.
Plans have also been floated for another 1200-1320 MW coal plant in Matarbari, phase III. These plans have been discussed by Coal Power Generation Company Bangladesh Limited,[1] and the project is also listed in the Bangladesh Master Plan, with a proposed commissioning of 2026.[2] However, there has been no developments on the project.
Contents
Location
The map below shows the location of the proposed Matarbari power station.[3][4][5]
Background on Matarbari
It was reported in March 2014 that "Coal Power Generation Company Bangladesh (CPGCB) will get $4.53 billion loan according to the agreement with Japanese donor agency Japan International Cooperation Agency (JICA) for the construction of a 1200MW coal-fired plant at Matarbari on Maheshkhali Island in Cox's Bazar."[4][6]
In February 2014, the Daily Star described the approximately $4 billion price-tag of the Matarbari project as "staggering." The paper reported that a feasibility study had been conducted for the project by Japan International Cooperation Agency (JICA) and Tokyo Electric Power (TEPC). According to the study, the cost was far higher than the 1320 MW Rampal power station, which would cost at least $1.5 billion. The reason for the high price of the Matarbari project is the additional components: river dredging, transmission, land acquisition (Tk350 crore), and a port on Sonadia Island capable of receiving and unloading large ships. Power would cost nearly Tk 7 per kilowatt hour when the plant goes into operation in 2023.[7]
According the Daily Star's report on the Jica/TEPCO feasibility study, the project would begin construction in 2017. The site has six threatened species, including one bird and five reptiles. The plant would use ultra-supercritical technology. Its cooling water would be discharged into the sea "at an ambient temperature." It would have "elaborate air and water pollution control arrangements." The study promised that the plant would provide "full electrification of the local community."[7]
The Daily Star reported the implementation process as follows:[7]
- As per the project's implementation schedule, the government needs to sign a loan agreement by late March and then appoint a consultant. But due to the volatile political situation since late last year, progress to this end has been stalled. Officials at this point are not sure about when the loan agreement could be signed and with whom.
The schedule also says that the basic design, bid documents preparation and floating of the tender for prequalifying power companies for this project would be done within next year and the contract would be awarded in 2016 so that a 52-month construction can begin in 2017.
However, in August 2014 the Planning Minister Mustafa Kamal announced that the Executive Committee of the National Economic Council (Ecnec) had approved the project and that the Japan International Cooperation Agency (JICA) funding for the project was US$3.8 billion as a "soft loan." The Minister stated that he hoped that the first 600MW unit of the plant would be commissioned in 2018.[8]
In January 2015 the project was approved as part of the government's priority-based "Fast-Track Projects".[9]
According to a February 2016 report, construction will begin in late 2016, with Sumitomo Corporation and Marubeni Corporation shortlisted to build the plant. The amount of the loan is US$3.7 billion, with an interest rate of 0.1 percent over 30 years after an initial 10-year grace period. The thermal efficiency of the plant is estimated at 41.3 percent.[10]
In November 2016 it was reported bidding between Marubeni Corporation and Sumitomo Corporation on constructing the plant would be extended to 2017.[11]
In January 2017 Marubeni and a consortium of Toshiba-Sumitomo submitted technical and financial bids for the US$4.5 billion coal project.[12] In May 2017 it was reported that the bids had been evaluated and the contract was expected to be awarded by June 2017 and physical works by July 2017.[13][14]
In June 2017 it was reported that Marubeni had been rejected as its financial offer was allegedly not satisfactory. The technical evaluation committee (TEC) of the project has recommended Sumitomo Corporation as the eligible bidder. A pre-contract negotiation with Sumitomo is supposed to be finalised within two months.[15]
In July 2017 it was reported construction by Sumitomo Corporation would begin in August 2017, with operation planned for 2024. Sumitomo will also build the Matarbari Port.[16]
In September 2017 it was reported that a Japanese consortium comprising Sumitomo Corporation, Toshiba Corporation, and IHI Corporation signed an engineering, procurement and construction (EPC) contract for the 1,200 MW coal-fired power plant. It was reported as under construction and is expected to be completed in July, 2024.[17][18] In March 2018 it was reported that "two percent of the main work of this plant has been done",[19] although it is preparatory land development work. The main construction work of the power plant is planned to start in 2020.[20]
In June 2018 the Japanese government approved a loan of US$608 million for the project, as part of its 39th Official Development Assistance (ODA) loan package.[21]
On June 30, 2019, Japan agreed to lend Bangladesh US$1.31 billion under an development assistance (ODA) loan package for the construction of the Matarbari coal plant.[22]
To develop the project, the ground needs to be raised 10 meters above mean sea level. In April 2019, it was reported that land development and channel excavation was 70% completed.[23] Planet satellite photos through September 22, 2019, show significant development on dredging and land clearing.
Phase II
In June 2019 it was reported that to reduce the production cost of Matarbari, another power plant will have to be constructed. According to EnergyBangla, "the per unit power production cost with imported coal will be around Tk. 6.5. But at Matarbari, the cost will be Tk 13.5. If another power plant is constructed then it will be able to use the same infrastructure. As a result, the production cost will fall."[24]
To establish this power plant, the government has asked loan assistance from Japan International Co-operation Agency (JICA). The power plant will be two additional units. It is planned that Sumitomo Corporation, Toshiba and IHI Corporation of Japan will build the plant. Reportedly 1608 acres of land have been acquired.[24]
Phase II is listed in the Bangladesh Master Plan, with a proposed commissioning of 2028.[25]
Maheshkhali power complex
Matarbari power station is part of a large multi-plant complex being organized by the Bangladesh Power Development Board (BPDB). In August 2013 the BPDB announced that it intended to develop a multi-plant power complex at Cox's Bazaar, including both coal-fired plants and combined cycle gas-fired plants. The announcement stated that the BPDB "intends to build 6000 MW Ultra Super Critical Coal Based Thermal Power Plant and 3000 MW LNG Based Combined Cycle Power Plant in different phases at Maheshkhali Upazila in Cox’s Bazar District." The announcement stated that the fuel for the projects would be imported coal and liquified natural gas. Five thousand acres were in the process of aqcquisition, situated within Amabassaya, Honanok and Panir Chhara mouza of Hoanok Union and Gharibhanga mouza of Kutubjhom union under Maheshkhali upazila, Cox’s Bazar. Ultra-supercritical technology would be employed by the coal plants, which would be sized at 600 to 1000 MW per unit.[26]
Project Details
- Sponsor: Coal Power Generation Company Bangladesh
- Parent company: Sumitomo Corporation
- Location: Maheshkhali Upazila, Cox's Bazar District, Chittagong, Bangladesh
- Coordinates: 21.7018395, 91.8834003 (exact)[3]
- Status: Permitted (Units 1&2), Announced (Units 3&4)
- Gross Capacity: 2400 MW (Units 1-4: 600 MW)[7]
- Type: Ultra-supercritical[27]
- Projected in service: 2024 (Units 1&2), 2028 (Units 3&4)
- Coal Type: Sub-bituminous[3]
- Coal Source: Imported
- Source of financing: Japan International Cooperation Agency (JICA)
Articles and resources
References
- ↑ "‘5,500 MW from Matarbari will bring revolutionary progress in Bangladesh’s power sector’," energynewsbd.com, September 30, 2018
- ↑ 2016 Master Plan "Revisited", Bangladesh Power Division, Nov 2018
- ↑ 3.0 3.1 3.2 "About CPGCBL: Project Brief," CPGCBL, accessed September 2015
- ↑ 4.0 4.1 "MATARBARI 1200MW POWER PROJECT: $4.3b loan deal in March likely" Progress Bangladesh, July 24, 2013.
- ↑ "Consulting Services for Design and Supervision of Matarbari Ultra Super Critical Coal-Fired Power Project" Coal Power Generation Company Bangladesh Limited (CPGCBL), February 2014.
- ↑ "JICA may finance Moheshkhali coal-fired power plant" The Financial Express, January 27, 2013.
- ↑ 7.0 7.1 7.2 7.3 "Maheshkhali to house massive power plant," Daily Star February 11, 2014
- ↑ "Target a complete electricity hub: Govt approves largest ever investment proposal for coal-based project near Maheshkhali", The Daily Star, August 13, 2014.
- ↑ "Matarbari Power Project and Paira Port Project included for fast track status," Bangladesh Awami League, Jan. 7, 2015
- ↑ Jagaran Chakma, "Japanese cos shortlisted for Matarbari power project," The Independent, 7 February 2016
- ↑ "Bidding time extended further," Daily Observer, Nov 25, 2016
- ↑ "Matarbari coal power project back on track," Daily Star, Mar 2, 2017
- ↑ Shahnaj Begum, "Sumitomo Corpn to get Matarbari power plant job," BD Observer, 15 May, 2017
- ↑ "Marubeni Lowest Bidder For Matarbari Power Plant," Energy Bangla, March 23, 2017
- ↑ "Matarbari power plant project in doldrums," Dhaka Tribune, June 22, 2017
- ↑ "Japan consortium to build power station, port in Bangladesh," Nikkei Asian Review, July 30, 2017
- ↑ "Consortium to build coal power plant, sea port at Matarbari," The Independent, Sep 27, 2017
- ↑ "Matarbari port to be turned into a deep-sea port," The Daily Star, Jan 7, 2018
- ↑ "No progress in 19 power plants yet," The Bangladesh Post, March 9, 2018
- ↑ "Work on Matarbari power plant goes fast," Bangladesh Post, October 16, 2018
- ↑ "Japan to provide Tk 15,326 crore for 6 projects," The Bangladesh Today, June 14, 2018
- ↑ "Japan to lend $1.31b for Matarbari power plant," Star Business Report, July 1, 2019
- ↑ "Dream Islands," Energy and Power, April 19, 2019
- ↑ 24.0 24.1 "Plan to construct 2nd power plant to reduce cost of Matarbari project," Energy Bangla, May 31, 2019
- ↑ 2016 Master Plan "Revisited", Bangladesh Power Division, Nov 2018
- ↑ ""Rendering Cconsultancy Services for Power Plant Projects at Maheshkhali Upazila in Cox's Bazar District of Bangladesh” Bangladesh Power Development Board, August 1, 2013.
- ↑ "Information Disclosure under new Guidelines" Japan International Cooperation Agency, accessed April 14, 2014.